Sensitivity analysis of key factors influencing concession period estimation in PPP wastewater treatment projects: a system dynamics approach
Main Article Content
Abstract
Population growth, combined with a lack of adequate financing, has led to the need for innovative infrastructure financing solutions in developing countries. The mechanism for dealing with these challenges has been, to a certain degree, made viable through the establishment of public–private partnerships (PPPs). This study aims to develop a system dynamics (SD) model using AnyLogic to determine the optimal concession period for wastewater treatment PPPs. The model incorporates construction costs, discount rates, construction duration, and pre-construction expenses to provide an integrative mode of decision-making. This model's application is demonstrated through a case study of the New Cairo Wastewater Treatment Plant, where the optimum concession period turned out to be 19 years. Sensitivity analysis showed that construction costs and discount rates are the most significant factors impacting the estimation of the concession period. The benefits of the SD approach were further validated through comparison with Monte Carlo simulations and agent-based modeling regarding capturing dynamic feedback mechanisms. The paper emphasizes the essence of adaptive governance and flexible contract structures that can help mitigate financial risks and build stakeholder confidence. The study presents practical recommendations to policymakers and practitioners.
Article Details
Section

This work is licensed under a Creative Commons Attribution 4.0 International License.
Authors who publish with this journal agree to the following terms:
a) Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution License that allows others to share and adapt the work with an acknowledgement of the work's authorship and initial publication in this journal.
b) Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
c) Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work (See The Open Access Citation Advantage Service). Where authors include such a work in an institutional repository or on their website (ie. a copy of a work which has been published in a UTS ePRESS journal, or a pre-print or post-print version of that work), we request that they include a statement that acknowledges the UTS ePRESS publication including the name of the journal, the volume number and a web-link to the journal item.
d) Authors should be aware that the Creative Commons Attribution (CC-BY) License permits readers to share (copy and redistribute the work in any medium or format) and adapt (remix, transform, and build upon the work) for any purpose, even commercially, provided they also give appropriate credit to the work, provide a link to the license, and indicate if changes were made. They may do these things in any reasonable manner, but not in any way that suggests you or your publisher endorses their use.
How to Cite
References
Altanany, M. Y., M. Badawy, G. A. Ebrahim, and A. Ehab. 2024. “Modeling and optimizing linear projects using LSM and Non-dominated Sorting Genetic Algorithm (NSGA-II).” Autom. Constr., 165: 105567. Elsevier. https://doi.org/10.1016/J.AUTCON.2024.105567.
Ameyaw, E. E., and A. P. C. Chan. 2015. “Risk allocation in public-private partnership water supply projects in Ghana.” Constr. Manag. Econ., 33 (3): 187–208. Routledge. https://doi.org/10.1080/01446193.2015.1031148.
Amiri-Pebdani, S., M. Alinaghian, and S. Safarzadeh. 2022. “Time-Of-Use pricing in an energy sustainable supply chain with government interventions: A game theory approach.” Energy, 255: 124380. https://doi.org/10.1016/j.energy.2022.124380.
Carbonara, N., N. Costantino, and R. Pellegrino. 2014. “Concession period for PPPs: A win–win model for a fair risk sharing.” Int. J. Proj. Manag., 32 (7): 1223–1232. Elsevier Ltd. https://doi.org/10.1016/j.ijproman.2014.01.007.
Castelblanco, G., P. Safari, and A. De Marco. 2023. “Driving Factors of Concession Period in Healthcare Public Private Partnerships.” Buildings. https://doi.org/https://doi.org/ 10.3390/buildings13102452.
Chen, H., L. Zhang, and X. Wu. 2020. “Performance risk assessment in public–private partnership projects based on adaptive fuzzy cognitive map.” Appl. Soft Comput., 93: 106413. https://doi.org/10.1016/j.asoc.2020.106413.
Contreras, C., and J. Angulo. 2018. “Government cost of extending concession term rights.” J. Infrastruct. Syst., 24 (3). https://doi.org/10.1061/(ASCE)IS.1943-555X.0000425.
Dai, T., Q. Wang, X. Sun, and B. Shi. 2020. “Study on investment return system of PPP wastewater treatment projects based on system dynamics.” Int. J. Technol. Policy Manag., 20 (3): 193–213. https://doi.org/10.1504/IJTPM.2020.109781.
Ehrlich, M., and R. T. L. Kong. 2008. “Modelling country reliability in Public Private Partnership infrastructure proejcts.” ISARC 2008 - Proc. from 25th Int. Symp. Autom. Robot. Constr., 751–758.
El-Kholy, A. M., and A. Y. Akal. 2021. “Assessing and allocating the financial viability risk factors in public-private partnership wastewater treatment plant projects.” Eng. Constr. Archit. Manag., 28 (10): 3014–3040. Emerald Publishing Limited. https://doi.org/10.1108/ECAM-05-2020-0373.
Eshun, B. T. B., A. P. C. Chan, and R. Osei-Kyei. 2021. “Conceptualizing a win–win scenario in public–private partnerships: evidence from a systematic literature review.” Eng. Constr. Archit. Manag., 28 (9): 2712–2735. https://doi.org/10.1108/ECAM-07-2020-0533.
Espinoza, R. D., and J. Rojo. 2015. “Using DNPV for valuing investments in the energy sector: A solar project case study.” Renew. Energy, 75: 44–49. Elsevier Ltd. https://doi.org/10.1016/j.renene.2014.09.011.
FahimUllah, T. M. Jamaluddin, S. S. M. E., and F. Nuria. 2018. “System Dynamics Model to Determine Concession Period of PPP Infrastructure Projects: Overarching Effects of Critical Success Factors.” J. Leg. Aff. Disput. Resolut. Eng. Constr., 10 (4): 4518022. American Society of Civil Engineers. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000280.
Feng, K., S. Wang, N. Li, C. Wu, and W. Xiong. 2018. “Balancing public and private interests through optimization of concession agreement design for user-pay PPP projects.” J. Civ. Eng. Manag., 24 (2): 116–129. https://doi.org/10.3846/jcem.2018.455.
Feng, K., S. Wang, C. Wu, G. Xia, and W. Hu. 2019. “Optimization of concession period for public private partnership toll roads.” Eng. Econ., 30 (1): 24–31. https://doi.org/10.5755/j01.ee.30.1.19215.
Grupo Banco Mundial. 2020. Wastewater: From Waste to Resource The Case of New Cairo, Egypt. Water Glob. Pract.
Guasch, J. L., J.-J. Laffont, and S. Straub. 2008. “Renegotiation of concession contracts in Latin America.” Int. J. Ind. Organ., 26 (2): 421–442. https://doi.org/10.1016/j.ijindorg.2007.05.003.
Guo, J., S. Hao, and X. Ren. 2016. “Concession Period Flexible Adjustment Mechanism Analysis Based on the Condition of Risk in a PPP Project.” ICCREM 2016 BIM Appl. Offsite Constr. - Proc. 2016 Int. Conf. Constr. Real Estate Manag., 822–828.
Guo, K., L. Zhang, and T. Wang. 2021. “Concession period optimisation in complex projects under uncertainty: a public–private partnership perspective.” Constr. Manag. Econ., 39 (2): 156–172. Routledge. https://doi.org/10.1080/01446193.2020.1849752.
Guo, Y., C. Chen, X. Luo, and I. Martek. 2024. “Determining concessionary items for ‘availability payment only’ PPP projects: a holistic framework integrating Value-For-Money and social values.” J. Civ. Eng. Manag., 30 (2): 149–167. https://doi.org/10.3846/jcem.2024.20841.
Hadi, A. H., and K. R. Erzaij. 2019. “Determination a Reasonable Concession Period for (PPP) Projects.” Civ. Eng. J., 5 (6): 1235–1248. https://doi.org/10.28991/cej-2019-03091328.
Hamidreza, A., N. Sajad, H. Abbasianjahromi, and S. Naserkhaki. 2023. “Using Agent-Based Modeling to Determine the Concession Period of BOT Contracts.” J. Infrastruct. Syst., 29 (2): 4023010. American Society of Civil Engineers. https://doi.org/10.1061/JITSE4.ISENG-2183.
Hanafizadeh, P., and V. Latif. 2011. “Robust net present value.” Math. Comput. Model., 54 (1): 233–242. https://doi.org/https://doi.org/10.1016/j.mcm.2011.02.005.
Hanaoka, S., and H. P. Palapus. 2012. “Reasonable concession period for build-operate-transfer road projects in the Philippines.” Int. J. Proj. Manag., 30 (8): 938–949. https://doi.org/https://doi.org/10.1016/j.ijproman.2012.02.001.
IFC. 2012. “Public-private partnerships conference june 6, 2012 | dakar, senegal.” PUBLIC-PRIVATE PARTNERSHIPS Conf. JUNE 6, 2012 | DAKAR, SENEGAL.
Javed, A. A., P. T. I. Lam, and A. P. C. Chan. 2014. “Change negotiation in public-private partnership projects through output specifications: an experimental approach based on game theory.” Constr. Manag. Econ., 32 (4): 323–348. https://doi.org/10.1080/01446193.2014.895846.
Jin, H., and C. Liu. 2023. “Incorporating Social Benefits in Concession Price Negotiation for Public–Private Partnership Contracts.” J. Leg. Aff. Disput. Resolut. Eng. Constr., 15 (1): 4522040. American Society of Civil Engineers. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000582.
Jin, H., S. Liu, J. Li, and C. Liu. 2020a. “A game-theoretic approach to developing a concession renegotiation framework for user-pays PPPs.” Int. J. Constr. Manag., 20 (6): 642–652. https://doi.org/10.1080/15623599.2020.1738003.
Jin, H., S. Liu, J. Li, and C. Liu. 2020b. “Imperfect Information Bargaining Model for Determining Concession Period of PPPs under Revenue Uncertainty.” J. Leg. Aff. Disput. Resolut. Eng. Constr., 12 (2). https://doi.org/10.1061/(ASCE)LA.1943-4170.0000382.
Jin, H., S. Liu, C. Liu, and N. Udawatta. 2019. “Optimizing the concession period of PPP projects for fair allocation of financial risk.” Eng. Constr. Archit. Manag., 26 (10): 2347–2363. https://doi.org/10.1108/ECAM-05-2018-0201.
Jin, H., S. Liu, J. Sun, and C. Liu. 2021. “Determining concession periods and minimum revenue guarantees in public-private-partnership agreements.” Eur. J. Oper. Res., 291 (2): 512–524. Elsevier B.V. https://doi.org/10.1016/j.ejor.2019.12.013.
Kamel, M., R. Khallaf, and I. Nosaier. 2023. “Net present value-time curve behaviour of public private partnership projects.” Int. J. Constr. Manag., 23 (11): 1924–1931. https://doi.org/10.1080/15623599.2022.2025742.
Kamel, M., A. Montaser, and I. A. El-Rashid. 2017. “Public Private Partnership in Egypt.” Proc. Can. Soc. Civ. Eng. Annu. Conf. (CSCE 2017), 6th CSCE/CRC Int. Constr. Spec. Conf. Vancouver, BC, Canada.
Khallaf, R., N. Naderpajouh, and M. Hastak. 2021. “Robust Decision-Making for Multiparty Renegotiations in Public-Private Partnerships.” J. Leg. Aff. Disput. Resolut. Eng. Constr., 13 (3). https://doi.org/10.1061/(ASCE)LA.1943-4170.0000473.
Li, J., and P. X. W. Zou. 2011. “Fuzzy AHP-based risk assessment methodology for PPP projects.” J. Constr. Eng. Manag., 137 (12): 1205–1209. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000362.
Ma, G., Q. Du, and K. Wang. 2018. “A Concession Period and Price Determination Model for PPP Projects: Based on Real Options and Risk Allocation.” Sustainability, 10 (3). https://doi.org/10.3390/su10030706.
Mamdoohi, S., E. Miller-Hooks, and J. Gifford. 2023. “An equilibrium approach for compensating public–private partnership concessionaires for reduced tolls during roadway maintenance.” Transp. Res. Part A Policy Pract., 175. https://doi.org/10.1016/j.tra.2023.103759.
Marques, R. C., and S. Berg. 2011. “Risks, Contracts, and Private-Sector Participation in Infrastructure.” J. Constr. Eng. Manag., 137 (11): 925–932. American Society of Civil Engineers (ASCE). https://doi.org/10.1061/(asce)co.1943-7862.0000347.
Mohy El Din, N. S. 2017. “An integrated framework approach for PPP projects in Egypt.” Master’s Thesis, the American University in Cairo.
Nguyen, A., A. Mollik, and Y.-Y. Chih. 2018. “Managing Critical Risks Affecting the Financial Viability of Public–Private Partnership Projects: Case Study of Toll Road Projects in Vietnam.” J. Constr. Eng. Manag., 144 (12). https://doi.org/10.1061/(ASCE)CO.1943-7862.0001571.
Nguyen, N., K. Almarri, and H. Boussabaine. 2021. “A risk-adjusted decoupled-net-present-value model to determine the optimal concession period of BOT projects.” Built Environ. Proj. Asset Manag., 11 (1): 4–21. Emerald Publishing Limited. https://doi.org/10.1108/BEPAM-12-2019-0134.
Nguyen, P. T., and V. Likhitruangsilp. 2017. “Identification risk factors affecting concession period length for public-private partnership infrastructure projects.” Int. J. Civ. Eng. Technol., 8 (6): 342–348.
Opawole, A., and G. O. Jagboro. 2018. “Compensation mechanisms for minimizing private party risks in concession-based public-private partnership contracts.” Int. J. Build. Pathol. Adapt., 36 (1): 93–120. https://doi.org/10.1108/IJBPA-09-2017-0041.
Planas, M. R. 2018. “The New Cairo Wastewater Treatment Plant (Egypt).” IESE Bus. Sch. Spec. Cent. PPP Smart Sustain. Cities, 173–186.
Qi, R., Z. Shen, and J. Wang. 2020. “Research on Government Compensation Mechanism of Public Rental Housing in Public Private Partnership Mode.” ICCREM 2020 Intell. Constr. Sustain. Build. - Proc. Int. Conf. Constr. Real Estate Manag. 2020, 501–512.
Sengupta, U. 2006. “Government intervention and public–private partnerships in housing delivery in Kolkata.” Habitat Int., 30 (3): 448–461. https://doi.org/10.1016/j.habitatint.2004.12.002.
Sharafi, A., M. Sadegh Amalnick, and A. Allah Taleizadeh. 2021. “Outcome of Financial Conflicts in the Operation Phase of Public-Private Partnership Contracts.” J. Constr. Eng. Manag., 147 (6). https://doi.org/10.1061/(ASCE)CO.1943-7862.0002011.
Song, J., S. Han, and D. Wang. 2008. “A Decision Method of Concession Period for Build-Operate-Transfer Projects of Sewage Treatment.” 2008 4th Int. Conf. Wirel. Commun. Netw. Mob. Comput., 1–4. IEEE.
Song, Y., L. Shangguan, and G. Li. 2021. “Simulation analysis of flexible concession period contracts in electric vehicle charging infrastructure public-private-partnership (EVCI-PPP) projects based on time-of-use (TOU) charging price strategy.” Energy, 228: 120328. https://doi.org/10.1016/j.energy.2021.120328.
Taha, G., A. Sherif, and M. Badawy. 2022. “Dynamic Modeling for Analyzing Cost Overrun Risks in Residential Projects.” ASCE-ASME J. Risk Uncertain. Eng. Syst. Part A Civ. Eng., 8 (3): 04022041. American Society of Civil Engineers. https://doi.org/10.1061/AJRUA6.0001262.
Thomas Ng, S., J. Xie, M. Skitmore, and Y. K. Cheung. 2007. “A fuzzy simulation model for evaluating the concession items of public–private partnership schemes.” Autom. Constr., 17 (1): 22–29. https://doi.org/https://doi.org/10.1016/j.autcon.2007.02.010.
Toma, H. M., S. El-Sayed, A. H. Ibrahim, and M. Badawy. 2024. “Hybrid Evaluation Model to assess the overall barriers of public-private partnership contracts.” Int. J. Constr. Manag., 1–10. Taylor & Francis. https://doi.org/10.1080/15623599.2024.2358584.
Ullah, F., B. Ayub, S. Q. Siddiqui, and M. J. Thaheem. 2016. “A review of public-private partnership: critical factors of concession period.” J. Financ. Manag. Prop. Constr., 21 (3): 269–300. https://doi.org/10.1108/JFMPC-02-2016-0011.
Ullah, F., and M. J. Thaheem. 2018. “Concession period of public private partnership projects: industry–academia gap analysis.” Int. J. Constr. Manag., 18 (5): 418–429. https://doi.org/10.1080/15623599.2017.1333400.
Wibowo, A. 2022. “VfM-at-Risk Analysis Model for Build–Operate–Transfer Infrastructure Projects.” J. Infrastruct. Syst., 28 (4): 4022032. American Society of Civil Engineers. https://doi.org/10.1061/(ASCE)IS.1943-555X.0000721.
Yu, S., T. Dai, Y. Yu, and J. Zhang. 2021. “Investment decision model of wastewater treatment public–private partnership projects based on value for money.” Water Environ. J., 35 (1): 322–334. https://doi.org/https://doi.org/10.1111/wej.12629.
Zhang, H., R. Jin, H. Li, and M. J. Skibniewski. 2018. “Pavement Maintenance–Focused Decision Analysis on Concession Periods of PPP Highway Projects.” J. Manag. Eng., 34 (1). https://doi.org/10.1061/(ASCE)ME.1943-5479.0000568.
Zhang, X. 2009. “Win–Win Concession Period Determination Methodology.” J. Constr. Eng. Manag., 135 (6): 550–558. American Society of Civil Engineers. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000012.
Zhang, X., and S. M. AbouRizk. 2006. “Determining a reasonable concession period for private sector provision of public works and service.” Can. J. Civ. Eng., 33 (5): 622–631. https://doi.org/10.1139/l06-010.
Zhang, Y., J. Yuan, J. Zhao, L. Cheng, and Q. Li. 2022. “Hybrid Dynamic Pricing Model for Transport PPP Projects during the Residual Concession Period.” J. Constr. Eng. Manag., 148 (2). https://doi.org/10.1061/(ASCE)CO.1943-7862.0002218.