Construction Economics and Building

Vol. 22, No. 1
March 2022


RESEARCH ARTICLE

Risks of Implementing Sustainable Construction Practices in the Nigerian Building Industry

Peter Uchenna Okoye1,*, Kevin Chuks Okolie1, Isaac Abiodun Odesola2

1 Department of Building, Nnamdi Azikiwe University, Awka, Nigeria

2 Department of Building, University of Uyo, Uyo, Nigeria

Corresponding author: Peter Uchenna Okoye, Department of Building, Nnamdi Azikiwe University, Awka, Nigeria, pu.okoye@unizik.edu.ng

DOI: https://doi.org/10.5130/AJCEB.v22i1.7420

Article History: Received: 11/09/2021; Revised: 09/12/2021, 11/02/2022; Accepted: 13/02/2022; Published: 21/03/2022

Abstract

This study assessed the risks level associated with implementation of sustainable construction practices through a questionnaire survey distributed to 256 building professionals in Nigeria. It identified 47 risk factors with different likelihood of occurrence and magnitude of impacts. A quantitative risk analysis result based on mean value method and risk prioritisation number showed that the three top-ranked risk factors with highest likelihood of occurrence were unavailability of sustainable materials and equipment, more complex and unfamiliar construction techniques and processes, and high initial sustainable construction costs; whereas the three top-ranked risk factors with highest magnitude of impacts were high initial sustainable construction costs, poor and inefficient communication among project participants, and high cost of sustainable materials and equipment. The criticality index result identified 23 critical risk factors which mostly related to knowledge and awareness, cost, regulatory framework, building materials and socioeconomic issues. However, the Wilcoxon Signed-rank test result indicated that there is significant difference (z = -3.207, p<0.001) between the likelihood of occurrence and magnitude of impacts of the risks factors associated with implementation of sustainable construction practices in Nigeria of which the effect was moderate (r = 0.468). Furthermore, the study revealed that there is no significance difference in the risk level of the risk factors associated with implementation of sustainable construction practices based on the respondents’ roles (p>0.05). The study, therefore, recommended for training of construction practitioners in the multi-risk management approaches and increasing awareness through education on sustainable construction concept for building industry stakeholders. It further recommended for developing of new sustainable and affordable building materials through research institutes like Nigerian Building and Road Research Institute (NBRRI) with appropriate regulatory and policy frameworks for successful sustainable building projects.

Keywords

Building Industry; Building Professionals; Implementation; Risk; Sustainable Construction

Introduction

Construction practice is inherently risky. The construction industry is widely known as one of the riskiest industries in the world (Mhetre, Konnur and Landage, 2016; Mohamed, 2017), due to its complexity, magnitude and time-consuming characteristics (Kang et al., 2015). The consequences of construction products and activities also come with huge environmental, social and economic burdens (Taroun, 2014; Xiahuo et al., 2018). In other words, the construction industry directly affects the society, environment and economy (Agyekum-Mensah, Knight and Coffey, 2012; Xia et al., 2015; Aghimien, Aigbavboa and Thwala, 2019), as a result, has the greatest impact on sustainability compared to any other industry (Willar et al., 2021). For example, the construction industry is responsible for 50% of global energy usage, 50% of global solid waste generation, 50% of global CO2 emitted into the atmosphere, 20-50% of global natural resources consumption, (Thomas, Costa and Guimarães, 2013; Reddy, 2016), and 40% of global extracted raw materials consumption (Bribian, Capilla and Uson, 2011). Construction activities increase the air and noise pollution, induce removal of vegetative cover, unsustainable water and energy consumption patterns, resource depletion, and sometimes altering or destroying the natural ecosystem (Cotgrave and Riley, 2013; Kibert, 2016; Reddy, 2016; Pearce, Ahn and HanmiGlobal., 2017; Wu et al., 2019a); in the course of meeting the population increase and rapid urbanisation demand (Kibert, 2016). Socio-economically, it consumes a huge amount of country’s annual budgets, usurps socioecological balance, and upsurges social cost and social risks (Liu et al., 2016; Danku et al., 2020).

However, the evolution of sustainable development concept and its application into the construction industry has led to the concept of sustainable construction. Sustainable construction is a novel approach adopted by the construction industry towards achieving sustainability (Koko and Bello, 2020). It represents the construction industry’s response to man’s concern over increasing consumption pattern in the mist of earth’s limited carrying capacity to sustain lives (Dania, 2016). Practically, sustainable construction deals with how the construction projects preserve the environment and affect the social and economic welfare of the people living around them (Willar et al., 2021). A sustainable construction uses less water, optimises energy efficiency, conserves natural resources, generates less waste, provides healthier spaces for occupants as well as reduces the impact of construction activities on human health and environment during the construction project’s lifecycle (U.S. Green Building Council (USGBC), 2010; Kanika et al., 2016). Contrarily, the conventional construction practices overlook the interrelationships between the construction facility, its components, surroundings, and users (Atombo, Dzantor and Agbo, 2015).

Sustainable construction practices, therefore, are the optimal utilisation of sustainable materials and technologies in the design, construction and operation of construction projects for social and economic wellbeing of the people without injury to the environment, now and in the future. Succinctly, sustainable construction practices are those activities, actions, processes, methods and policies adopted during construction processes so as to ensure a balance between environment, economy and society throughout the life cycle of a construction project both now and in the future. It entails following a suitable practice in choosing and sourcing materials, and construction methodologies, as well as design philosophy to improve performance, decrease environmental burden of the project, minimise waste, and become ecologically friendlier; while taking into consideration environmental, economic and socio-cultural values (Mohamed and El-Meligy, 2013).

Unfortunately, the implementation of sustainable construction practices is not an easy task (Willar et al., 2021), especially in the developing countries like Nigeria where construction processes are structured within the traditional construction framework (Kibert, 2016). Sustainable construction projects require the use of advanced construction techniques (Murtagh, Scott and Fan, 2020), complex design and materials (Olawumi and Chan, 2018), and greater communication network among construction project stakeholders (Wuni and Shen, 2020). Just as with the traditional construction projects, sustainable construction projects face many risks (Hwang et al., 2017; Qazi, et al., 2021). Construction risk is, therefore, multifaceted (Wang, Dulami and Agar, 2004) and uncertain event or condition (Hilson and Simon, 2020). It is the likelihood of the occurrence of combination of events/factors or a definite event/factor, which occur during the whole process of construction to the detriment of the project (Kasapoğlu, 2018).

Meanwhile, risk in the construction project may result to substantial cost and time overruns that are detrimental to the project objectives, and inherent in any construction project. Adverse effect of risks in the construction project could lead to losses not only to the project owners, contractors or society, but also to the professionals who are engaged in the project (Kasapoğlu, 2018). However, sustainability specific risks are unique because they are generally not reflected on the risk checklists and risk matrices, unlike traditional risks related to the short-term project performance measures (Qazi, et al., 2021). Furthermore, sustainability-related risks are associated with a wide range of probability and impact ratings due to the evolving and complex nature of these risks (Guan, Abbasi and Ryan, 2020).

The unpredictability of construction site conditions, multiple stakeholders’ involvement and volatile demand of construction projects make the sustainable construction process riskier (Kasapoğlu, 2018). Apine and Valdés (2017) opine that risks in sustainable construction practices are growing with increasing utilisation of new materials and technology in the field. This has even grown to the extent that it is raising health and safety concerns (Fortunate III et al., 2012; Onubi, Yusof and Hassan, 2020) and thereby, constituting an additional risk to the project. Davies and Davies (2017) reveal that risk is one of the barriers of implementing sustainable construction practices in the construction projects. It was also acknowledged that the implementation of sustainable construction practices is bedevilled with a lot of challenges and risks; especially to those who are new to sustainable construction operational system (Apine and Valdés, 2017; Ismael and Shealy, 2018). To this end, sustainable construction project requires a high level of collaboration between the construction stakeholders more than the traditional construction project due to increased number of uncertainty and risk (Klotz and Horman, 2010).

Since the construction managers are still learning and adapting to embrace sustainable practices (Qazi, et al., 2021) and also sustainability-related risks in the construction projects are quite different from the traditional risks (Mahdiyar et al., 2020), it is very germane to assess the risks of implementing sustainable construction practices. It is against this backdrop that this study was aimed at assessing the risks associated with the implementation of sustainable construction practices in Nigeria with a view to increasing the construction managers’ understanding and successes of implementing the dynamics of sustainable construction principles. This would allow for appropriate risk response planning and control (El-Sayegh et al., 2018), and minimises the probability of occurrence of unexpected events in executing sustainable building projects (Javed et al., 2020). Based on the foregoing, two hypotheses were postulated to direct the path of this study.

Hypothesis 1:

Ho: There is no significant difference between the likelihood of risks occurrence and magnitude of risks impact of risks associated with the implementation of sustainable construction practices.

H1: There is significant difference between the likelihood of risks occurrence and magnitude of risks impact of risks associated with the implementation of sustainable construction practices.

Hypothesis 2:

Ho: There is no significance difference in the perceived risk level based on the respondents’ roles in the implementation of sustainable construction practices.

H1: There is significance difference in the perceived risk level based on the respondents’ roles in the implementation of sustainable construction practices.

The remainder of the paper is organised as follows: a brief overview of the relevant literature, the methodology applied in the study, the result of the study, the discussion and implications of the study, and the conclusions, recommendations and future research directions.

Literature Review

Currently, there is an increasing awareness over the benefits of implementing sustainable construction principles in all facets of building project delivery process. There is also fear of inherent risks associated with sustainable construction projects and limiting effectiveness of efforts toward sustainable construction objectives (Chan, Darko and Ameyaw, 2017). Construction projects often fail due to unforeseen risks (Górecki and Díaz-Madroñero, 2020). Undoubtedly, different studies (Rafindadi et al., 2014; Ismael and Shealy, 2018) have affirmed that sustainable construction projects are engrossed with enormous risks. Hwang, Shan and Supa’at (2017) even revealed that adoption of sustainable construction presents additional risks to the building projects. Study by Ranaweera and Crawford (2010) found that sustainable building projects incur a higher financial risk compared to the conventional building projects due to a higher investment resulting from the adoption of environmental strategies as requirements for sustainable buildings. Hwang et al. (2017) also found that sustainable buildings projects are facing risks at a more critical level than the conventional building projects. However, from the 42 identified risks, Hwang et al. (2017) revealed that complex procedures to obtain approvals, overlooked high initial cost, unclear requirements of owners, employment constraint, and lack of availability of green materials and equipment were top five critical risks in sustainable building construction projects.

Similarly, Apine and Valdés (2017) found higher operating expenses, unachievable project requirements, failure to meet green code or green certification requirements, construction schedule and cost impacts, damage to environmental and professional reputation, materials and equipment with reduced life cycles or immediate aesthetic or performance failure as risks associated with the sustainable buildings projects. El-Sayegh et al. (2018) categorised 30 identified risks into five groups: management, technical, green team, green materials and regulatory/economic, and found the top five risks associated with sustainable construction projects to include: shortage of clients’ funding, insufficient or incorrect sustainable design information, design changes, unreasonable tight schedule for sustainable construction and poor scope definition in sustainable construction.

From the list of 52 risk elements developed, Ismael and Shealy (2018) found that lack of public awareness was the risk that occurs most, whereas designers’ and contractors’ inexperience has the greatest negative impact on the implementation of sustainable construction in Kuwaiti construction industry. However, the study found high cost of sustainable materials and equipment, contractors’ inexperience with sustainable construction, lack of practical experience, lack of public awareness and high initial sustainable construction costs as top five risks of sustainable construction. It recommended for educational interventions, changes in risk allocation, and behavioural science to reframe upfront costs and long-term saving as possible solutions. Qin, Mo and Jing (2016) surveyed different risk factors (including political risks, social risks, quality/technological risks, certification risks, financial/cost risks and managerial risks) associated with green buildings and found 56 risk factors, among which 36 were perceived as key risk factors affecting the success of sustainable buildings. Likewise, Zhao, Hwang and Gao (2016) identified 28 risk factors which they grouped into 11 groups. They found that inaccurate cost estimation was the top risk factor, while cost overrun risk was the most critical risk group. However, the study found that the overall risk criticality was high, signifying the importance of risk management in green construction projects. An in-depth summary of risks associated with implementing sustainable construction practices from the forgoing literature and other sources is presented in Table 1. These would form the basis for further analysis.

Table 1. Summary of Risks Associated with Implementing Sustainable Construction Practices
Code Risk Factors Sources
SCR1 Uncertain government policies Ismael and Shealy, 2018; Zou, Zhang and Wang, 2007
SCR2 Cost estimation inaccuracy Ismael and Shealy, 2018; Qin, Mo and Jing, 2016; Zhao, Hwang and Gao, 2016; Zou and Couani, 2012
SCR3 Payback period is too long Durmus-Pedini and Ashuri, 2010; Gurgun, Arditi and Casals Vilar, 2016; Ismael and Shealy, 2018
SCR4 Uncertainty in the performance of sustainable buildings projects Apine and Valdés, 2017; Yin et al., 2018
SCR5 High cost of sustainable materials and equipment Hwang and Ng, 2013; Ismael and Shealy, 2018
SCR6 Cost and time overrun due to lack of sustainable building knowledge Gurgun, Arditi and Casals Vilar, 2016; Gurgun, et al., 2018; Ismael and Shealy, 2018
SCR7 Lack of sustainable construction management experts Zhao, Hwang and Gao, 2016
SCR8 Unattainable expectations or requirements Hwang et al., 2015; Gurgun, Arditi and Casals Vilar, 2016
SCR9 Culture issues Kasapoğlu, 2018
SCR10 Poor and inefficient communication among project participants Zou and Couani, 2012; Qin, Mo and Jing, 2016; Zhao, Hwang and Gao, 2016
SCR11 Liable to undue claims Durmus-Pedini and Ashuri, 2010; Tollin, 2011
SCR12 Complex approval process due to sustainability specifications Zou and Couani, 2012; Qin, Mo and Jing, 2016; Zhao, Hwang and Gao, 2016; Gurgun, Arditi and Casals Vilar, 2016; Hwang et al., 2017
SCR13 Lack of practical experience Qin, Mo and Jing, 2016; Ismael and Shealy, 2018; Kasapoğlu, 2018
SCR14 Unavailability of sustainable materials and equipment Zou and Couani, 2012; Hwang et al., 2017; Ismael and Shealy, 2018
SCR15 Uncertainty in the quality and performance of sustainable materials Apine and Valdés, 2017
SCR16 Change in material types and specifications during construction Apine and Valdés, 2017
SCR17 Lack of sustainable technical experts Zou and Couani, 2012; Qin, Mo and Jing, 2016; Zhao, Hwang and Gao, 2016
SCR18 Unforeseen sustainable projects requirements Durmus-Pedini and Ashuri, 2010; Qin, Mo and Jing, 2016
SCR19 Lack of public awareness and knowledge Ismael and Shealy, 2018
SCR20 Unclear contract conditions for claims, litigations and dispute resolution Durmus-Pedini and Ashuri, 2010; Zhao, Hwang and Gao, 2016
SCR21 Safety and health issues Fortunate et al., 2012; Zou and Couani, 2012; Paradis and Tran, 2016; Zhao, Hwang and Gao, 2016; Kasapoğlu, 2018; Cardoso et al., 2019
SCR22 Fluctuations in labour and material rate Qin, Mo and Jing, 2016; Kasapoğlu, 2018
SCR23 Lack of market demand Durmus-Pedini and Ashuri, 2010; Kasapoğlu, 2018
SCR24 Lack of political support Ismael and Shealy, 2018
SCR25 High initial sustainable construction costs Zou and Couani, 2012; Qin, Mo and Jing, 2016; Hwang et al., 2017; Ismael and Shealy, 2018
SCR26 Cost of investment in skills development and shortage of skills Qin, Mo and Jing, 2016; Hwang et al., 2017
SCR27 High sustainable construction premiums Robichaud and Anantatmula, 2011; Gurgun, Arditi and Casals Vilar, 2016
SCR28 Additional responsibilities for construction maintenance Zhao, Hwang and Gao, 2016; Apine and Valdés, 2017
SCR29 Project delay due to incremental time caused by sustainable construction Apine and Valdés, 2017; Yin et al., 2018
SCR30 More complex and unfamiliar construction techniques and processes Zou and Couani, 2012; Zou and Zhao, 2014; Yang, Zou and Wang, 2016
SCR31 Undue interventions of clients Zhao, Hwang and Gao, 2016
SCR32 Changing sustainable building certification procedures and policies Qin, Mo and Jing, 2016
SCR33 Disputes arising from additional requirements Zou and Couani, 2012; Zhao, Hwang and Gao, 2016
SCR34 Lack of planning and early consideration of sustainability measures by stakeholders Bal et al., 2013
SCR35 Failure to meet sustainable construction certification requirements Gurgun et al., 2016; Apine and Valdés, 2017; Qazi, et al., 2021
SCR36 Lack of qualified professionals with requite sustainable building expertise Zou and Couani, 2012; Gurgun, Arditi and Casals Vilar, 2016; Qin, Mo and Jing, 2016; Zhao, Hwang and Gao, 2016
SCR37 Insufficient or incorrect sustainable design information Qin, Mo and Jing, 2016; Zhao, Hwang and Gao, 2016; El-Sayegh et al., 2018
SCR38 Unreasonable tight schedule for sustainable construction Apine and Valdés, 2017; El-Sayegh et al., 2018
SCR39 Exposed to litigation for not achieving client expectations Tollin, 2011; Qin, Mo and Jing, 2016; Kasapoğlu, 2018
SCR40 Shortage of clients’ funding Qin, Mo and Jing, 2016; Zhao, Hwang and Gao, 2016; El-Sayegh et al., 2018
SCR41 Project team inexperience in providing sustainable construction services Gurgun, Arditi and Casals Vilar, 2016; Ismael and Shealy, 2018
SCR42 Insecurity Paradis and Tran, 2016; Kasapoğlu, 2018
SCR43 Corruption and high crime rate Zhao, Hwang and Gao, 2016
SCR44 Uncertainty in energy saving and renewable energy Gurgun, Arditi and Casals Vilar, 2016
SCR45 Poor scope definition and unclear allocation of roles in sustainable construction Gurgun, Arditi and Casals Vilar, 2016; Qin, Mo and Jing, 2016; Hwang et al., 2017; El-Sayegh et al., 2018
SCR46 Inflation and fluctuation of exchange rate Zhao, Hwang and Gao, 2016; Kasapoğlu, 2018; Qazi, et al., 2021
SCR47 Design changes during construction El-Sayegh et al., 2018

In the developing countries, these risks are more pronounced than in the developed ones due to the low level of awareness and understanding of sustainable construction concept (Abolore, 2012; Afolayan and Tunde, 2014). Wang et al. (2016) argued that low level of awareness leads to limited knowledge and in turn irrational behaviour. Consequently, construction practitioners are reluctant to change and tend to be risk averse (Kibert, 2016; Hammond et al., 2019). Aghimien, Aigbavboa and Thwala (2019) and Susanti, Filestre and Juliantina (2019) also revealed that fear of increased cost of investment, inadequate knowledge and understanding of the concept of sustainability, limited number of trained and/or certified workers and lack of communication between parties are some of the major challenges of implementing sustainable construction in the developing countries. Therefore, sustainable construction creation depends on the awareness, understanding of the consequences of individual actions, quest for knowledge and absolute involvement and commitment to the principle (Abidin, 2010; Abolore, 2012). Awareness then includes revealing the risks of implementing sustainable construction practices. According to Kibert (2016), lack of knowledge and/or experience prevents practitioners from identifying all the risks related to sustainable construction practices. Notwithstanding, risk management literature on sustainable construction practices is still insufficient to allow professionals and practitioners to understand and identify the risks involved in implementing sustainable construction practices (Apine and Valdés, 2017).

The complexity and potency of sustainability-related risks indicated the importance of effective management of these risks so as to achieve the desired sustainability goals, allocate budgets, and target certification levels (Gurgun, Arditi and Casals Vilar, 2016). Sequel to this, Durmus-Pedini and Ashuri (2010) recommended for hiring professionals who are experienced in green buildings and engaging consultants to minimise the impacts of risks related to green construction. Likewise, Zou and Couani (2012) recommended for the utilisation of expertise of green building professionals in managing green construction risks. However, implementation of new or untested green technologies and products can be challenging, particularly if, the professionals using them have limited knowledge (Gurgun, Arditi and Casals Vilar, 2016).

Juxtaposing the level of awareness and understanding of sustainable construction concept vis-à-vis the structure of the building construction industry and current construction practices in Nigeria, it could be argued that construction practitioners are not yet very conversant with the risks related to implementation of sustainable construction practices. This therefore, has resulted to the low level of implementation of sustainable construction principles in the Nigerian construction industry (Chukwu, 2018; Otali and Oladokun, 2018). Although Hwang et al. (2017) and El-Sayegh et al. (2018) claimed that sustainable construction projects are riskier than the traditional projects due to greater complexity and uncertainty inherent in the sustainable construction projects, Wu et al. (2019b) revealed that sustainability like other project performance measures such as time, cost and quality, has also been assessed through the risk management perspective to prioritise the associated risks. Notwithstanding, research efforts on the risks associated with sustainable construction projects are still very limited (Qin, Mo and Jing, 2016; Hwang, Shan and Supa’at, 2017; Guan, Abbasi and Ryan, 2020). In Nigeria, there is no clear evidence of research directed towards assessing the risk of implementing sustainable construction practices in the literature.

Available literature has focused on the risk management in construction projects (Wang, Dulami and Agar, 2004; Banaitiene and Banaitis, 2012; Kasapoğlu, 2018; Bahamid, Doh and Al-Sharaf, 2019), risk assessment and prioritisation techniques (Qin, Mo and Jing, 2016; Zhao, Hwang and Gao, 2016; Tong et al., 2018; Yuan et al., 2018; Ribas et al., 2019; Guan, Abbasi and Ryan, 2020; Qazi, et al., 2021), managing risks in green building (Zou and Couani, 2012), risks in green building projects (Durmus-Pedini and Ashuri, 2010; Xiang and Shu, 2018), impact of green building (Gurgun, Arditi and Casals Vilar, 2016), risk perception (Wu et al., 2019b). Most of these studies were also conducted outside the shores of Nigeria. Although Qazi et al. (2021) dealt with prioritising the risks in sustainable construction projects in United Arab Emirates, Qin et al. (2016) investigated the risks associated with the life cycle of green buildings in China. This study would focus on the risks associated with the implementation processes of sustainable construction practices in South-East Nigeria. It should be noted that the management and administration of construction project is key to achieving its objectives. Unarguably, sustainable construction projects cannot be effectively implemented without first identifying and assessing the risks therein. Besides, construction professionals who are not familiar with the sustainable construction concepts and approaches may perceive it as risky (Ismael and Shealy, 2018). This study, therefore, narrows the gap of risks of implementing sustainable construction practices in the literature.

Methodology

Research design

The study adopted a descriptive survey research design because, the study was only interested in determining the type of risks associated with the process of implementation of sustainable construction projects. Additionally, a survey approach was adopted because it is efficient, flexible, has ethical advantage, internal and external validity, and can be used to cover geographically spread samples such as in this study (Mathers, Fox and Hunn, 2009). However, it depends on the accuracy of the sampling frame. In this case, it involved the collection of information on the level of risk associated with the implementation of sustainable construction practices (exposure and impact of risk factors) as they exist on the building construction sites in South-East Nigeria. Although the South-East Nigeria is just one region in Nigeria, it was chosen because it is the fastest growing region among the six regional blocks in Nigeria with very high volume of ongoing building projects. Moreover, construction operational system is the same in all parts of Nigeria. The study area is the most densely populated region in Nigeria with an average density of 442 persons per square kilometre (Federal Government of Nigeria (FGN), 2012).

The study made use of structured questionnaire administered to the selected building construction professionals in the study area. Although, other methods such as interview, observation and Delphi, can also be used, questionnaire is the most efficient data collection mechanism when the researcher knows exactly what is required and how to measure the variables of interest (Sekaran and Bougie, 2016). Since the study was only interested in the risk level of different risk factors affecting implementation of sustainable construction practices and not ‘why’, questionnaire is the most appropriate tool that ensures minimal bias and wider spread. The questionnaire was designed to measure the perceived risk level of sustainable construction practices in Nigeria. It was also designed to investigate the perceived likelihood of occurrence and the impact of risk factors affecting the implementation of sustainable construction practices in Nigeria. Considering the frequency and severity simultaneous indicates a broader result than evaluating risk based on frequency or on severity only (Baradan and Usmen, 2006). Meanwhile, the questionnaire consisted of two parts. Part 1 captured the respondents’ demographic data. Part 2 contained 47 risk factors for sustainable construction practices extracted from the literature and on which perceived likelihood of occurrence and magnitude of impacts were assessed. The respondents were asked to express their opinion based on their perception on the frequency of occurrence and severity of impact of identified risk factors affecting the implementation of sustainable construction practices on a 5-point Likert scale. Where, 1 = very unlikely, 2 = unlikely, 3 = fairly unlikely, 4 = likely, 5 = very likely (for likelihood of risk occurrence); and 1 = very insignificant, 2 = insignificant, 3 = fairly significant, 4 = significant, 5 = very significant (for severity of risk impact).

Sampling and sampling technique

The population of this study constituted all relevant registered building industry professionals as obtained from the register of various professional associations in South-East Nigeria and have practised for at least 10 years. In this kind of research, experience of the respondents on the subject matter is very important to avoid any suspicion of bias. It is also believed that those professionals with sufficient practical experience of at least 10 years could be able to provide the desired information about the risks inherent in the process of implementation of sustainable construction practices, because they may have handled varieties of building projects that should have given them enough insights about the risks associated with sustainable construction projects. According to Ismael and Shealy (2018), lack of experience of designers and contractors is the risk element with the highest possible negative impact on future sustainable construction projects. The importance of using experienced construction professionals in identifying and assessing the risks inherent in sustainable construction projects before implementation has also been stressed by Durmus-Pedini and Ashuri (2010), Zou and Couani (2012) and Kibert (2016). Specifically, Wu et al. (2019b) revealed that professionals’ experience in the sustainable construction projects affected their risk perceptions. Thus, a total of 728 professionals was involved. To determine the appropriate sample size for this study, Cochran’s sample size calculation procedure for large population was used as shown in Equation 1 (Cochran, 1977).

Eqn001.png   (1)

Where n0 is the sample size, t = value for selected alpha level of .025 in each tail = 1.96 (the alpha level of .05 indicates the level of risk the researcher is willing to take that true margin of error may exceed the acceptable margin of error), (p)(q) = estimate of variance = 0.25 (maximum possible proportion (0.5) x 1-maximum possible proportion (0.5) produces maximum possible sample size), d = acceptable margin of error for proportion being estimated = 0.05 (error estimate).

However, if the computed sample size is greater than 5% of the population (n0 > 5% of population), the final and survey sample size would be calculated using Cochran (1977) correction formula in Equation 2. Otherwise n0 would be adopted as the final and survey sample size for the study.

Eqn002.png   (2)

From Equation 1,

The sample size Eqn002a.png

Since n0 (385) > 5% of 728 (36),

The survey sample size Eqn002b.png

Prior to the distribution of the questionnaires, the locations and contacts of the prospective respondents were first identified and consent/permission was sought and obtained from the relevant persons. The objectives of the study were clearly stated in the consent/introduction letter and no further permission was necessary for data collection through the questionnaire in this study. The study then employed a multi-stage sampling procedure in selecting the desired respondents. Firstly, cluster sampling technique was employed, where the samples were proportionally divided into five to ensure that the respondents from each of the five states in the study area were adequately represented in the survey (geographical spread). Secondly, a simple random sampling technique was used in choosing the respondents from each state (cluster). Meanwhile, with the initial set out benchmark of ≥ 10 years of experience, it was assumed that any respondent selected through a simple random sampling was appropriate and capable of giving valid information.

Based on this, a total of 256 copies of questionnaire were distributed to the respondents through both self-administration and by online post via established mail contacts. After about one month of the distribution of questionnaires, very few responses were obtained. Consequently, soft reminder was sent to the respondents who had not responded to the questionnaires through phone calls and emails. Two other reminders were sent to the respondents at one-month interval. Unfortunately, COVID-19 pandemic restricted the researchers from making personal contacts to the respondents which later affected the response rate. The distribution and retrieval of questionnaire were conducted from April to July 2020. Thereafter, 162 questionnaires were returned with 117 representing about 45.70% found valid for used in the analysis due to their completeness and meeting other criteria (≥ 10 years of practice). Although the valid response rate was below the sample size, Dörnyei (2007) recommended that in a descriptive survey research design a sample of between 1% and 10% of the population, with a minimum of 100 respondents is acceptable and can produce a valid result. Wiseman (2003) and Archer (2008) also noted that web-based surveys often encounter low response rates. However, the result of this study may suffer from generalisability (Young, 2016). Since the population of this study is finite (728), the result of this study is reliable and acceptable within a 5% margin of error and at 95% confidence level as recommended by Bartlett, Kotrlick and Higgins (2001); Gilliland and Melfi (2010) and Taherdoost (2017) for survey research.

Method of data analysis

The data generated from the survey were subjected to descriptive analysis. Thereafter, a quantitative risk analysis was carried out to assess the risk factors. Table 2 summarised a modified risk factor likelihood of occurrence and impact rating scales respectively, based on the Royal Institute of Chartered Surveyors (RICS) Professional Guidance for Management of Risk (RICS, 2015).

Table 2. Risk Factor Likelihood of Occurrence and Risk Factor Impact Scales
Risk Factor Likelihood of Occurrence Risk Factor Impact Scale
Scale Rating Description Scale Rating Description
1 Very unlikely Extremely unlikely to happen. 1 Very insignificant Minimal impact that can be easily remedied
2 Unlikely Low but not impossible. 2 Insignificant Minor and shot-term impact on the achievement of objectives
3 Fairly likely Fairly likely to happen. 3 Fairly significant Reduced viability and medium-term impact on the achievement of objectives.
4 Likely More likely to occur than not. 4 Significant Serious or major impact on the achievement of objectives.
5 Very likely Almost certain to occur. 5 Very significant Critical impact on the achievement of objectives.

RICS (2015)

However, the likelihood of risk occurrence and severity of risk impact were calculated using the Mean Value Method as shown in Equations 3 and 4.

Eqn003.png   (3)

Eqn004.png   (4)

Where LROi = the likelihood assessment of risk i; Eqn004a.png = the likelihood assessment of risk i by respondents j; SRIi = the impact assessment of risk i; Eqn004b.png = the impact assessment of risk i by respondents j; and n = the total number of respondents.

On the other hand, the degree of risk or rather the risk score is obtained using Risk Criticality Index (RCI) in Equations 5 and 6, which invariably determines the level of risk (risk prioritisation number). The Risk Criticality Index has been extensively used in the risk management-related studies (Deng, Pheng and Zhao, 2014; Hwang et al., 2017; Hwang, Shan and Supa’at, 2017).

Eqn005.png   (5)

Eqn006.png   (6)

Where RCIi = the risk criticality of risk i; Eqn006a.png = the risk criticality of risk i by respondents j; and n = the total number of respondents.

Since the assessment of LRO and SRI were both carried out based on 5-point rating system (5X5 matrix), the RCI is therefore, on a full scale of 25. In this study, a benchmark for critical risks in implementing sustainable construction practices in the study area is presented in Table 3. In this case, any risk factor with score greater than 12 was classified as high-level risk and therefore, considered as critical risk factor (see Table 3).

Table 3. Classification of Risk Level
Risk score scale Risk level
1 ≤ x ≤ 4 Low
4 < x ≤ 12 Medium
12 < x ≤ 25 High

x = Actual risk score for each factor

Workplace Safety and Health Council (2011)

As argued in the introduction, a null and alternative hypothesis of significant difference between the likelihood of risks occurrence and magnitude of risks impact of risks associated with the implementation of sustainable construction practices were tested using Wilcoxon Signed-rank test statistic. Meanwhile, Kruskal-Wallis test statistics was applied to test the differences in the risk level based on the respondents’ role

Decision: Reject H0 if p<0.05 otherwise, do not reject H0 and conclude.

Result

Respondents background information

The respondents composed of more than half (58.97%) working in the private sector organisations, while about (41.03%) work in the public sector organisations. Out of this number, 15.38% were affiliated to building profession, 28.21% to architecture profession, 34.19% belong to engineering, whereas 22.22% belong to quantity surveying profession. Similarly, 11.97% of the respondents were holding either the post of project or construction managers, 36.75% were either project/site engineer, architect, quantity surveyor or builder. 17.95% were holding the post of project consultants, 14.53% were academia, 11.11% supervisors, and 7.69% were directors.

Furthermore, 19.66% of the respondents stated that they had diploma as the highest educational certificate. 40.17% showed that they had first degree certificates, 7.35% had master’s degree, 9.40% had PhD as their highest certificate, while 3.42% had other certificates. This showed that all the respondents were lettered and could give account of themselves in terms of response to the questions in this study. In terms of years of experience, the benchmark for consideration was (> 10 years). In this case, 28.21% indicated that they have had between 11-15 years working experience, more than half (58.97%) of the respondents indicated that they have had between 16-20 years working experience, while 12.82% indicated that they have had more than 20 years of working experience. This implied that the respondents are very relevant, well positioned and had requite experience in the construction practice to give vital information and express their perception about the risks associated with implementation of sustainable construction practices.

Likelihood, Impact and Criticality of Risks Associated with Implementation of Sustainable Construction Practices

Table 4 showed the result of analysis of risk associated with implementation of sustainable construction practices in South-East Nigeria. The result revealed that out of the 47 identified risk factors from the literature, only one risk factor (i.e., unavailability of sustainable materials and equipment) with mean score value of 4.58 occurred very likely, 26 factors with mean scores ranging from 4.48-3.51 occur likely, whereas 20 factors with mean scores ranging from 3.47-2.62 fairly likely or occasionally occurred. Likewise, only one risk factor with mean score value of 4.67 (i.e., high initial sustainable construction costs) had very significant impact on the implementation of sustainable construction practices. 21 risk factors had significant impact with mean scores ranging from 4.43-3.68, 18 risk factors had fairly significant impact with mean score ranging from 3.42-2.50, while 7 risk factors with mean scores ranging from 2.48-2.26 had insignificant impact.

However, the top five ranked risk factors with the highest likelihood of occurrence in the implementation of sustainable construction practices were unavailability of sustainable materials and equipment (4.58), more complex and unfamiliar construction techniques and processes (4.48), high initial sustainable construction costs (4.37), failure to meet sustainable construction certification requirements (4.35), and uncertain government policies (4.34). Similarly, the top five ranked risk factors with the greatest magnitude of impact were high initial sustainable construction costs (4.37), poor and inefficient communication among project participants (4.43), high cost of sustainable materials and equipment (4.39), lack of public awareness and knowledge (4.39) and lack of sustainable technical experts (4.25).

In terms of risk level, 23 risk factors were classified as high-level risk factors with RCI ranging from 20.41-12.37, while 24 factors with RCI ranging from 11.76-6.79 were medium level risk factors. However, the 23 high level risk factors were also critical risk factors which have overall critical effects on the implementation of sustainable construction practices. As also contained in Table 4, the top five critical risk factors affecting implementation of sustainable construction practices in South-East Nigeria in order of criticality were high initial sustainable construction costs (20.41), unavailability of sustainable materials and equipment (19.34), lack of public awareness and knowledge (18.88), high cost of sustainable materials and equipment (18.75), and failure to meet sustainable construction certification requirements (18.40).

Table 4. Assessment of risks associated with implementation of sustainable construction practices
Code LRO SRI RCI Overall Ranking Risk Level
Mean Rank Frequency Rating Mean Rank Impact Rating
SCR1 4.34 5 Likely 4.21 9 Significant 18.27 6 High
SCR2 3.51 27 Likely 2.70 33 Fairly significant 9.48 33 Medium
SCR3 3.91 21 Likely 2.90 30 Fairly significant 11.34 28 Medium
SCR4 3.97 19 Likely 2.91 29 Fairly significant 11.55 27 Medium
SCR5 4.27 8 Likely 4.39 3 Significant 18.75 4 High
SCR6 3.94 20 Likely 3.14 27 Fairly significant 12.37 23 High
SCR7 4.21 10 Likely 2.76 31 Fairly significant 11.62 25 Medium
SCR8 3.08 34 Fairly likely 3.17 26 Fairly significant 9.76 31 Medium
SCR9 3.20 31 Fairly likely 3.01 28 Fairly significant 9.63 32 Medium
SCR10 3.05 35 Fairly likely 4.43 2 Significant 13.51 20 High
SCR11 3.26 30 Fairly likely 4.11 13 Significant 13.40 21 High
SCR12 4.15 14 Likely 4.23 6 Significant 17.55 9 High
SCR13 4.11 16 Likely 3.90 19 Significant 16.03 15 High
SCR14 4.58 1 Very likely 4.22 8 Significant 19.34 2 High
SCR15 4.19 12 Likely 3.92 18 Significant 16.42 13 High
SCR16 4.20 11 Likely 4.15 12 Significant 17.43 10 High
SCR17 4.16 13 Likely 4.25 5 Significant 17.68 7 High
SCR18 2.97 39 Fairly likely 3.96 15 Significant 11.76 24 Medium
SCR19 4.30 6 Likely 4.39 3 Significant 18.88 3 High
SCR20 3.91 21 Likely 3.42 23 Fairly significant 13.37 22 High
SCR21 4.14 15 Likely 3.89 20 Significant 16.10 14 High
SCR22 3.72 26 Likely 3.68 22 Significant 13.69 19 High
SCR23 3.27 29 Fairly likely 2.48 41 Insignificant 8.11 36 Medium
SCR24 3.76 24 Likely 2.69 34 Fairly significant 10.11 29 Medium
SCR25 4.37 3 Likely 4.67 1 Very significant 20.41 1 High
SCR26 2.97 39 Fairly likely 2.29 46 Insignificant 6.80 46 Medium
SCR27 3.11 33 Fairly likely 2.60 35 Fairly significant 8.09 37 Medium
SCR28 3.47 28 Fairly likely 2.38 44 Insignificant 8.26 35 Medium
SCR29 3.74 25 Likely 2.26 47 Insignificant 8.45 34 Medium
SCR30 4.48 2 Likely 3.24 24 Fairly significant 14.52 18 High
SCR31 2.94 41 Fairly likely 2.38 44 Insignificant 6.99 45 Medium
SCR32 2.90 42 Fairly likely 2.58 37 Fairly significant 7.48 41 Medium
SCR33 3.04 37 Fairly likely 2.50 40 Fairly significant 7.60 40 Medium
SCR34 2.82 44 Fairly likely 2.51 39 Fairly significant 7.08 44 Medium
SCR35 4.35 4 Likely 4.23 6 Significant 18.40 5 High
SCR36 4.30 6 Likely 4.10 14 Significant 17.63 8 High
SCR37 2.78 46 Fairly likely 4.16 11 Significant 11.56 26 Medium
SCR38 2.85 43 Fairly likely 2.55 38 Fairly significant 7.27 43 Medium
SCR39 2.81 45 Fairly likely 2.73 32 Fairly significant 7.67 38 Medium
SCR40 4.23 9 Likely 3.86 21 Significant 16.62 12 High
SCR41 4.04 17 Likely 3.93 17 Significant 15.88 16 High
SCR42 2.62 47 Fairly likely 2.59 36 Fairly significant 6.79 47 Medium
SCR43 3.86 23 Likely 3.96 15 Significant 15.29 17 High
SCR44 2.98 38 Fairly likely 2.45 42 Insignificant 7.30 42 Medium
SCR45 3.05 35 Fairly likely 3.21 25 Fairly significant 9.79 30 Medium
SCR46 4.01 18 Likely 4.20 10 Significant 16.84 11 High
SCR47 3.15 32 Fairly likely 2.42 43 Insignificant 7.62 39 Medium

To determine the significant difference between the likelihood of occurrence and magnitude of impact of risk factors affecting implementation of sustainable construction practices, the Wilcoxon Signed-rank test result is showed in Tables 5 and 6. The result rejected the null hypothesis of no significant difference and concluded that there is significant difference (z = -3.207, p<0.001) between the likelihood of occurrence and magnitude of impact of risk factors affecting implementation of sustainable construction practices in the study area. In this case, the LRO has a larger median (3.76) than SRI median (3.24) which suggested the existence of statistically significant difference. The result also suggested that the overall risk level in the implementation of sustainable construction practices was more likely determined by the likelihood of risk occurrence than the magnitude of risk impact.

Table 5. Result of Mean Rank from Wilcoxon Signed-Ranks Test
Ranks LRO SRI
N Mean Rank Sum of Ranks
SRI - LRO Negative Ranks 34a 25.50 867.00
Positive Ranks 13b 20.08 261.00
Ties 0c
Median 3.76 3.24
Total 47

a. SRI < LRO

b. SRI > LRO

c. SRI = LRO

Table 6. Result of Wilcoxon Signed-Ranks Test
Test Statisticsb
SRI - LRO
Z -3.207a
Asymp. Sig. (2-tailed) .001
Exact Sig. (2-tailed) .001
Exact Sig. (1-tailed) .001
Point Probability .000

a. Based on positive ranks.

b. Wilcoxon Signed Ranks Test

To further determine the magnitude of the differences, the effect size (r) was computed by dividing the absolute (positive) standardised test statistic (z) by the square root of the number of factors (N) as represented in Equation 7.

Therefore, Image5796.png   (7)

Where, z = 3.207 and N = 47

Thus, Eqn007b.png

From the foregoing result, the effect size was 0.468 which is a moderate effect according to Cohen’s classification of effect sizes which is 0.1 (small effect), 0.3 (moderate effect) and ≥0.5 (large effect). This result suggested that the differences in the likelihood of occurrence and magnitude of impact of risk factors affecting implementation of sustainable construction practices in the study area could be due to disparities in the tripod of sustainable construction practices.

Furthermore, to determine if there is significance difference in the risk level of the risk factors associated with implementation of sustainable construction practices based on the respondents’ roles, the Kruskal-Wallis test statistics result presented in Table 7 revealed that the computed χ2 was 9.335 and the p value (0.096) is greater than 0.05 at 5% significant level. This implied that there is no significance difference in the risk level of risk factors associated with the implementation of sustainable construction practices based on the respondents’ roles.

Table 7. Kruskal Wallis H Test for comparing the risk level based on the respondents’ role
Role of respondent N Mean Rank
Construction manager 14 38.71
Project/site engineer, architect, quantity surveyor or builder 43 64.44
Project consultants 21 64.10
Academia 17 64.35
Supervisor 13 59.54
Director 9 41.78
Total 117
Test Statisticsa,b
Risk level
Chi-Square 9.335
df 5
Asymp. Sig. .096

a. Kruskal Wallis Test

b. Grouping Variable: Role of respondents

Discussion

Risk level of sustainable construction projects

The result of this study has demonstrated that the risks associated with sustainable construction projects are many and varied. The study also indicated that different elements of sustainable construction are associated with different dimensions and magnitudes of risk factors in operationalising sustainability in the building industry. Specifically, the study showed that both high and medium level risk factors are associated with sustainable construction practices. The study further revealed that 23 out of 47 risk factors are high level and critical risk factors, whereas 24 were medium level risk factors. This, therefore, implied that the implementation of sustainable construction practices in Nigeria especially in the study area needs to be cautious. This is because the result indicated that many risk factors are contending with implementation of sustainable construction practices most of which are critical to the success of sustainable construction projects. This result aligned with that of Bahamid, Doh and Al-Sharaf (2019) who identified 111 risk factors with 56 being critical to the success of construction projects in developing countries. The result further implied that the high-level risk factors affecting implementation of sustainable construction practices must be considered, measured and controlled so as to reduce them to an acceptable level before adventuring into sustainable building projects. At the same time, the medium level risk factors have to be tamed to a minimal level of acceptance so as to maximise the full benefit of sustainable construction projects.

However, when the risk level of implementing sustainable construction practices in the study area was compared based on the role of the respondents, the Kruskal-Wallis test statistics result revealed that there is no significance difference in the risk level of the risk factors associated with the implementation of sustainable construction practices based on the respondents’ roles. This suggested that the respondents perceived the risks associated with the implementation of sustainable construction practices in the study area as the same regardless of the role they play in the construction project. This result corroborated with Ismael and Shealy (2018) whose result indicated that there were no significant differences in the mean scores for all risk categories in sustainable construction projects between the different titles of the professionals (project manager, site engineer, or architect) in Kuwait. Since all the respondents were professionals in the building industry, the tendency of perceiving any difference in the risk inherent in any construction project is likely to be slim because professionally, they perform near similar roles in the project. The path of their training is also similar, hence the likelihood of non-significance difference in their perception about the risk level in the implementation of sustainable construction practices as indicated by this study. This result is similar to the result of Ribas et al. (2019) who found that different groups in hydroelectric plant construction project have similar risk perceptions, despite having different roles and asymmetric risk sharing caused mainly by the characteristics and provisions contained in the Engineering, Procurement and Construction (EPC) contract. It also agreed with Zou and Couana (2012) whose result suggested that members of green building supply chain invest in green building training and education regarding responsibilities.

Critical risk factors associated with implementation of sustainable construction practices

The study identified 23 critical risk factors associated with the implementation of sustainable construction practices. This study identified seven critical factors relating to knowledge and awareness of sustainable construction, five critical factors relating to cost of sustainable construction projects, and three critical factors relating to sustainable materials and equipment. It also identified five critical factors relating to government policies and regulations for implementation of sustainable construction practices, and three critical factors relating to socioeconomic factors. This result suggested to the importance of sustainable construction knowledge and awareness among the building professionals, operational and suitable regulatory framework, and proper assessment of availability of sustainable construction resources including the prevailing socioeconomic conditions/implications surrounding the implementation of sustainable construction practices. This result is supported by Zhao, Hwang and Gao (2016) who assessed the risk of green projects in Singapore. The high number of critical risk factors suggested that they could be responsible for the low implementation of sustainable construction practices in the execution of building projects in the study area. This implied that those critical risk factors must be considered in the planning and execution of sustainable construction projects. For instance, knowledge and awareness about sustainable construction is a capital issue when it comes to the implementation of sustainable construction practices. At least sustainable construction project involves a huge amount of initial capital outlay and requires sound technical and professional expertise with supporting regulatory frameworks. This result is aligned with the results of Wang et al. (2016), Aghimien, Aigbavboa and Thwala (2019) and Susanti, Filestre and Juliantina (2019).

More significantly, since the critical risk factors were mostly knowledge and awareness related, cost related, policy and regulation related, material and equipment related, and socioeconomic related, it could be argued that the fundamental issues relating to the implementation of sustainable construction practices in the study area have not been adequately addressed; thus, the perception of construction professionals. Implicitly, lack of awareness and knowledge about sustainable construction concepts could be the reason while construction professionals perceived the implementation of sustainable construction practices as risky. This could also be the source of low interest in sustainable construction on the part of the government, professionals and other relevant stakeholders in terms of development of regulatory and policy frameworks. In addition, the perceived high cost and unavailability of materials and equipment, lack of technical experts, and socioeconomic risks could be reason for the low level of implementation of sustainable construction practices. This view is supported by Kibert (2016) and Ismael and Shealy (2018). Consequently, there is need to raise the bar of training and education of building construction professionals and other relevant stakeholders on issues relating to sustainable construction so as to increase their knowledge and awareness.

Furthermore, the significance of all the 47 identified risk factors was centred on the fact that none was a low-level risk factor. This implied that none of these risk factors should be ignored while planning for implementation of sustainable construction practices in the study area. However, a multiple risk control mechanism should be adopted according to the nature and degree of riskiness of each factor. This is in line with the provision of the Risk Assessment Methodology of the University of Melbourne, Australia (2017) which stated that risks are controlled using a combination of control measures and must be implemented in accordance with the risk control priorities established during the risk assessment. Overall, the result suggested that the level of risk associated with the implementation of sustainable construction practices is more related to the rate of likelihood of occurrence than the magnitude of impact, but in any case careful risk assessment must be undertaken before any consideration for embarking on sustainable construction building project.

Rate of occurrence and impact of risk factors associated with implementation of sustainable construction practices

Although the result revealed that all the identified risk factors were either classified as high or medium level risk factors, the result of the Wilcoxon Signed-rank test showed that there is significant difference between the likelihood of occurrence and magnitude of impact of risks associated with implementation of sustainable construction practices. This implied that the rate of occurrence and magnitude of impact differed across factors. The result also revealed that some factors have high frequency of occurrence, while some others have high severity of impact and vice versa. The result supported Zou and Couana (2012) who found that the risks in green building development vary and are unequally distributed throughout the supply chain. This could be attributed to the differences and multiplicity of sustainable construction practices, in which environmental, social and economic sustainability criteria must be integrated and considered simultaneously. It also gave credence to the fact that risk management in construction industry is multifaceted, and therefore, requires multiple risk management approaches. This is related to the findings of Apine and Valdés (2017) which suggested that different tools should be applied in managing sustainable building projects and supported by El-Sayegh et al. (2018).

Particularly, the top risk factors with high rate of frequency of occurrence (e.g. unavailability of sustainable materials and equipment, more complex and unfamiliar construction techniques and processes, high initial sustainable construction costs, failure to meet sustainable construction certification requirements, and uncertain government policies), and high severity of impact factors (e.g. high initial sustainable construction costs, poor and inefficient communication among project participants, high cost of sustainable materials and equipment, lack of public awareness and knowledge and lack of sustainable technical experts) respectively, suggested that different approaches need to be applied in the management of risks associated with implementation of sustainable construction practices. This finding is in line with that of Hwang et al. (2017) and Ismael and Shealy (2018). However, since this study indicated that the rate of occurrence of the risks factors contributed slightly more than the magnitude of impacts to the overall risk level, it then suggested that more attention should be focused on such factors that contributed mostly to the overall risk level.

Conclusion

The concept of sustainable construction is still new to the Nigerian construction industry. Its level of implementation in the building industry has also been found to be very low due to numerous barriers including the risks associated with it. Therefore, the need for an insight into the risk level of implementing sustainable construction practices in the Nigeria building industry. The study has therefore, assessed the risk level of implementing sustainable construction practices in South-East Nigeria. It has found that the risks associated with the implementation of sustainable construction practices are many and varied. It has further found that these risks have different likelihoods of occurrence and magnitudes of impacts depending on the variability of the risk factors and elements of sustainability. Furthermore, the study established 23 critical risk factors associated with the implementation of sustainable construction practices in study area. Besides, it has succeeded in prioritising the risk levels and risk factors associated with the implementation of sustainable construction practices in South-East Nigeria. It then argued that these factors must not be overlooked when considering the execution of sustainable construction building projects for optimum sustainability performance and benefits.

Specifically, certain factors related to knowledge and awareness, cost, regulatory framework, construction materials and socioeconomic issues call for special attention, while implementing sustainable construction practices. This suggested that sustainable construction concept has not been deeply rooted in the Nigerian building construction industry. Therefore, there is need for more awareness of sustainable construction among building industry stakeholders. This could be done through education and training, collaboration and knowledge sharing, and other communication channels. This also calls for the need for more research into developing new sustainable building materials and making them available and affordable. Furthermore, the need for appropriate regulatory framework and socioeconomic policies that would guide the implementation of sustainable construction practices is of very essence.

Certainly, this study has provided some positive practical implications. Specifically, it has contributed to both practice and research in risk management of sustainable construction projects and Nigeria construction industry in general. Although the study did not evaluate risk management strategies, it has provided valuable information and basis for developing appropriate guidelines for holistic management of risks associated with sustainable construction projects. In view of this, the study craves for the development of multifaceted strategies for curbing or mitigating the risks associated with implementation of sustainable construction practice, especially the high-level risk factors. Since this study has classified and prioritised the risks associated with implementation of sustainable construction practices, it is a useful asset to the construction industry stakeholders especially the clients, construction managers, professionals and contractors who mostly receive the risk impacts in construction projects. The study is also a valuable tool to regulatory agencies, academia in the built environment and building material research agencies.

On the strength of this result, the study recommended for a multi-risk management approach incorporating element of sustainable construction for construction managers since the frequency of risk occurrence and the magnitude of risk severity differ due to the variability of risk factors and elements of sustainability. It also suggested for a special training on issues relating to risks management of sustainable construction projects and awareness of sustainable construction concept among building industry stakeholders. Finally, it recommended for the development of appropriate regulatory framework for management of sustainable construction projects and intensified efforts towards developing new sustainable and affordable building materials through building material research institutes like Nigerian Building and Road Research Institute (NBRRI).

References

Abidin, N.Z., 2010. Investigating the awareness and application of sustainable construction concept by Malaysian developers. Habitat International, [e-journal] 34(4), pp.421–26. https://doi.org/10.1016/j.habitatint.2009.11.011

Abolore, A.A., 2012. Comparative study of environmental sustainability in building construction in Nigeria and Malaysia. Journal of Emerging Trends in Economics and Management Sciences (JETEMS), 3(6), pp.951-61.

Afolayan, G.P. and Tunde, A.M., 2014. Sustainable infrastructure provision through awareness in selected medium-sized towns in Kwara State, Nigeria. In: D. Szymańska and S. Środa-Murawska, eds. Bulletin of Geography: Socio-economic Series, [e-journal] 25, pp.7-14. https://doi.org/10.2478/bog-2014-0026

Aghimien, D., Aigbavboa, C. and Thwala, W., 2019. Microscoping the challenges of sustainable construction in developing countries. Journal of Engineering, Design and Technology, [e-journal] 17(6), pp.1110-28. https://doi.org/10.1108/JEDT-01-2019-0002

Agyekum-Mensah, G., Knight, A. and Coffey, C.H., 2012. 4Es and 4 poles model of sustainability: Redefining sustainability in the built environment. Structural Survey, 30(5), pp.426-42. https://doi.org/10.1108/02630801211288206

Apine, A. and Valdés, F.J.E., 2017. Risk management in sustainable project in the construction industry: Cases of Swedish companies. Master Thesis. Umeå School of Business and Economics, Sweden.

Archer, T.M., 2008. Response rates to expect from web-based surveys and what to do about it. Journal of Extension, 46(3), pp.1–6. Available at: http://www.joe.org/joe/2008june/rb3.php [Accessed 8 December 2021].

Atombo, C., Dzantor, J.C.K. and Agbo, A.A., 2015. Integration of sustainable construction in project management: A case study in Ghana. International Journal of Construction Engineering and Management, [e-journal] 4(1), pp.13-25. https://doi.org/10.5923/j.ijcem.20150401.02

Bahamid, R.A., Doh, S.I. and Al-Sharaf, M.A., 2019. Risk factors affecting the construction projects in the developing countries. IOP Conference Series: Earth and Environmental Science, [e-journal] 244, p.012040. https://doi.org/10.1088/1755-1315/244/1/012040

Bal, M., Bryde, D., Fearon, D. and Ochieng, E., 2013. Stakeholder engagement: Achieving sustainability in the construction sector. Sustainability, [e-journal] 5(2), pp.695-710. https://doi.org/10.3390/su5020695

Banaitiene, N. and Banaitis A., 2012. Risk management in construction projects. In: Banaitiene, N. ed. Risk Management - Current Issues and Challenges. Intechopen, pp.429-48. https://doi.org/10.5772/51460

Baradan, S. and Usmen, M.A., 2006. Comparative injury and fatality risk analysis of building trades. Journal of Construction Engineering and Management, [e-journal] 132(5). https://doi.org/10.1061/(ASCE)0733-9364(2006)132:5(533)

Bribian, I.Z., Capilla, A.V. and Uson, A.A., 2011. Life cycle assessment of building materials: Comparative analysis of energy and environmental impacts and evaluation of the ecoefficiency improvement potential. Building and Environment, [e-journal] 46(5), pp.1133-40. https://doi.org/10.1016/j.buildenv.2010.12.002

Bartlett, J.E., Kotrlick, J.W. and Higgins, C.C., 2001. Organisational research: Determining appropriate sample size in survey research. Information Technology, Learning, and Performance Journal, 19(1), pp.43-50.

Cardoso, L., Araujo, N., Brea, J.A.F. and Dieguez-Soto, J., 2019. Benefits and risks of green jobs in the construction industry. Journal of Scientific and Industrial Research, 78(3), pp.254-57.

Chan, A.P.C., Darko, A. and Ameyaw, E.E., 2017. Strategies for promoting green building technologies adoption in the construction industry – An international study. Sustainability, [e-journal] 9, p.969. https://doi.org/10.3390/su9060969

Chukwu, I., 2018. Sustainability in the Nigerian construction industry: The feasibility of adopting green building rating system. PhD. Indiana State University, Terre Haute, Indiana.

Cochran, W.G., 1977. Sampling techniques. 3rd ed. New York: John Wiley & Sons Inc.

Cotgrave, A.J. and Riley, M. eds., 2013. Total sustainability in built environment. London, UK: Palgrave Macmillan. https://doi.org/10.1007/978-0-230-39059-1

Dania, A.A., 2016. Sustainable construction at the firm level: Case studies from Nigeria. PhD. School of Construction Management and Engineering, University of Reading. Available at: http://centaur.reading.ac.uk/72754/1/18028935_Dania_thesis.pdf [Accessed 28 November 2021].

Danku, J.C., Adjei-Kumi, T., Baiden, B.K. and Agyekun, K., 2020. An exploratory study into social cost consideration in Ghanaian construction industry. Journal of Building Construction and Planning Research, [e-journal] 8(1), pp.14-29. https://doi.org/10.4236/jbcpr.2020.81002

Davies, O.O.A. and Davies, I.O.E., 2017. Barriers to implementation of sustainable construction techniques. MAYFEB Journal of Environmental Science, 2, pp.1-9.

Deng, X., Pheng, L.S. and Zhao, X., 2014. Project system vulnerability to political risks in international construction projects: The case of Chinese contractors. Project Management Journal, [e-journal] 45, pp.20-33. https://doi.org/10.1002/pmj.21397

Dörnyei, Z., 2007. Research methods in applied linguistics. Oxford: Oxford University Press.

Durmus-Pedini, A. and Ashuri, B., 2010. An overview of the benefits and risk factors of going green in existing buildings. International Journal of Facility Management, 1(1), pp.1-15.

El-Sayegh, S.M., Manjikian, S., Ibrahim, A., Abouelyousr, A. and Jabbour, R., 2018. Risk identification and assessment in sustainable construction projects in the UAE. International Journal of Construction Management, [e-journal]. https://doi.org/10.1080/15623599.2018.1536963

Federal Government of Nigeria. 2012. Nigeria’s path to sustainable development through green economy. Country report to the Rio + 20 Summits, June. Available at: https://sustainabledevelopment.un.org/content/documents/1023nigerianationalreport.pdf. [Accessed 29 November 2021].

Fortunate III, B.R., Hallowell, M.R., Behm, M. and Dewlaney, K., 2012. Identification of safety risks for high-performance sustainable construction projects. Journal of Construction Engineering and Management, [e-journal] 138(4), pp.499-508. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000446

Gilliland, D. and Melfi, V., 2010. A note on confidence interval estimation and margin of error. Journal of Statistics Education, [e-journal] 18(1), pp.1-8. https://doi.org/10.1080/10691898.2010.11889474

Górecki, M. and Díaz-Madroñero, M., 2020. Who risks and wins? - Simulated cost variance in sustainable construction projects. Sustainability, [e-journal] 12(8), p.3370. https://doi.org/10.3390/su12083370

Guan, L., Abbasi, A. and Ryan, M.J., 2020. Analysing green building project risk interdependencies using interpretive structural modelling. Journal of Cleaner Production, [e-journal] 256, p.120372. https://doi.org/10.1016/j.jclepro.2020.120372

Gurgun, A.P., Arditi, D. and Casals Vilar, P., 2016. Impacts of construction risks on cost in Leed-certified projects. Journal of Green Building, [e-journal] 11(4), pp.163-81. https://doi.org/10.3992/jgb.11.4.163.1

Gurgun, A.P., Bayhan, H.G., Polat, G. and Turkoglu, H., 2018. Schedule risk assessment in green building projects. Proceedings of International Structural Engineering and Construction, [e-journal] 5(1), pp.13.1-13.6. https://doi.org/10.14455/ISEC.res.2018.50

Hammond, S.F., Savage, D.A., Gajendran, T. and Maund, K., 2019. Stakeholders embrace green construction as the right direction: But as individuals they make self-interested decisions. CIB World Building Congress, 17-21 June 2019, Hong Kong SAR, China.

Hilson, D. and Simon, P., 2020. Practical Project Risk Management. The ATOM Methodology. Oakland, CA: Berrett-Koehler Publishers.

Hwang, B.G. and Ng, W.J., 2013. Project management knowledge and skills for green construction: Overcoming challenges. International Journal of Project Management, [e-journal] 31(2), pp.272–84. https://doi.org/10.1016/j.ijproman.2012.05.004

Hwang, B.G., Shan, M., Phua, H. and Chi, S., 2017. An exploratory analysis of risks in green residential building construction projects: The case of Singapore. Sustainability, [e-journal] 9(7), p.1116. https://doi.org/10.3390/su9071116

Hwang, B.G., Shan, M. and Supa’at, N.N.B., 2017. Green commercial building projects in Singapore: Critical risk factors and mitigation measures. Sustainable Cities and Society, [e-journal] 30, pp.237-47. https://doi.org/10.1016/j.scs.2017.01.020

Hwang, B.G., Zhao, X. See, Y.L. and Zhong, Y., 2015. Addressing risks in green retrofit projects: The case of Singapore. Project Management Journal, [e-journal] 46, pp.76-89. https://doi.org/10.1002/pmj.21512

Ismael, D. and Shealy, T., 2018. Sustainable construction risk perceptions in the Kuwaiti construction industry. Sustainability, [e-journal] 10(6), p.1854. https://doi.org/10.3390/su10061854

Javed, N., Thaheem, M.J., Bakhtawar, B., Nasir, A.R., Khan, K.I.A. and Gabriel, H.F., 2020. Managing risk in green building projects: Toward a dedicated framework. Smart and Sustainable Built Environment [e-journal] 9(2), pp.156-73. https://doi.org/10.1108/SASBE-11-2018-0060

Kang, B.G., Faazlie, M.A., Goh, B.H., Song, M.K. and Zhang, C., 2015. Current practice of risk management in the Malaysia construction industry – The process and tool/techniques. International Journal of Structural and Civil Engineering Research, 4(4), pp.371-77. https://doi.org/10.18178/ijscer.4.4.371-377

Kanika, Singh, K., Rana, K. and Dahiya, M., 2016. A comparative study on green and conventional buildings. International Journal of Home Science, 2(2), pp338-43.

Kasapoğlu, E., 2018. Risk management in construction. In: A. Almusaed, ed. Sustainable Buildings Interaction between a Holistic Conceptual Act and Materials Properties. London, UK: IntechOpen. https://doi.org/10.5772/intechopen.76341

Kibert, C.J., 2016. Sustainable construction: Green building design and delivery. 4th ed. Hoboken, NJ: John Wiley and Sons Inc.

Klotz, L. and Horman, M., 2010. Counterfactual analysis of sustainable project delivery processes. Journal of Construction Engineering and Management, [e-journal] 136(5), pp.595-605. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000148

Koko, A.F. and Bello, M., 2020. Exploring the factors hindering the use of green architecture in Nigeria. In: J.A.P. Arcas, C. Rubio-Bellido, A. Pérez-Fargallo and I. Oropeza-Perez, eds. Zero-Energy Buildings - New Approaches and Technologies, IntechOpen. https://doi.org/10.5772/intechopen.92403

Liu, Z., Zhu, Z., Wang, H. and Huang, J., 2016. Handling social risks in government-driven mega project: An empirical case study from West China. International Journal of Project Management, [e-journal] 34(2), pp.202-18. https://doi.org/10.1016/j.ijproman.2015.11.003

Mahdiyar, A., Mohandes, S.R., Durdyev, S., Tabatabaee, S. and Ismail, S., 2020. Barriers to green roof installation: An integrated fuzzy-based MCDM approach. Journal of Cleaner Production, [e-journal] 269, p.122365. https://doi.org/10.1016/j.jclepro.2020.122365

Mathers, N., Fox, N. and Hunn A., 2009. Surveys and questionnaires. The National Institute for Health Research (NIHR) Research Design Service for the East Midlands/Yorkshire & the Humber. Available at: https://www.rds-yh.nihr.ac.uk/wp-content/uploads/2013/05/12_Surveys_and_Questionnaires_Revision_2009.pdf [Accessed 10 November 2021].

Mhetre, K., Konnur, B.A. and Landage, A.B., 2016. Risk management in construction industry. International Journal of Engineering Research, [e-journal] 5(1), pp.153-55. https://doi.org/10.17950/ijer/v5i1/035

Mohamed, A.S.Y. and El-Meligy, D.A.A., 2013. Sustainability tomorrow in construction materials and technologies. IACSIT International Journal of Engineering and Technology, [e-journal] 5(1), pp.25-31. https://doi.org/10.7763/IJET.2013.V5.503

Mohamed, H.A., 2017. Occupational hazards and their relation with health problems among construction building workers at El Sherouk City. American Journal of Nursing Research, [e-journal] 5(3), pp.96-103. https://doi.org/10.12691/ajnr-5-3-4

Murtagh, N., Scott, L. and Fan, J., 2020. VSI editorial - Sustainable and resilient construction: Current status and future challenges. Journal of Cleaner Production, [e-journal] 268, p.122264. https://doi.org/10.1016/j.jclepro.2020.122264

Olawumi, T.O. and Chan, D.W.M., 2018. Identifying and prioritising the benefits of integrating BIM and sustainability practices in construction projects: A Delphi survey of international experts. Sustainable Cities and Society, [e-journal] 40, pp.16-27. https://doi.org/10.1016/j.scs.2018.03.033

Onubi, H.O., Yusof, N.A. and Hassan, A.S., 2020. Adopting green construction practices: Health and safety implications. Journal of Engineering, Design and Technology, [e-journal] 18(3), pp.635-52. https://doi.org/10.1108/JEDT-08-2019-0203

Otali, M. and Oladokun, M.G., 2018. Evaluation of level of adoption of sustainability practices among construction firms in the Niger Delta States of Nigeria. Journal of Construction Project Management and Innovation, 8(1), pp.1711–37.

Paradis, R. and Tran, B., 2016. Balancing security/safety and sustainability objectives. Washington: National Institute of Building Sciences. Available at: https://www.wbdg.org/resources//balancing-securitysafety-and-sustainability-objectives. [Accessed 5 December 2019].

Pearce, A.R, Ahn, Y.H. and HanmiGlobal Co, Ltd., 2017. Sustainable buildings and infrastructure. London: Routledge. https://doi.org/10.9774/gleaf.9781315562643

Qazi, A., Shamayleh, A., El-Sayegh, S. and Formaneck, S., 2021. Prioritizing risks in sustainable construction projects using a risk matrix-based Monte Carlo Simulation approach. Sustainable Cities and Society, [e-journal] 65, p.102576. https://doi.org/10.1016/j.scs.2020.102576

Qin, X., Mo, Y. and Jing, L., 2016. Risk perceptions of the life-cycle of green buildings in China. Journal of Cleaner Production, [e-journal] 126, pp.146-58. https://doi.org/10.1016/j.jclepro.2016.03.103

Rafindadi, A.D., Mikić, M., Kovaćić, I. and Cekić, Z., 2014. Global perception of sustainable construction project risks. Procedia – Social and Behavioural Sciences, [e-journal] 119, pp.456-65. https://doi.org/10.1016/j.sbspro.2014.03.051

Ranaweera, R. and Crawford, R.H., 2010. Using early-stage assessment to reduce the financial risks and perceived barriers of sustainable buildings. Journal of Green Building, [e-journal] 5(2), pp.129-46. https://doi.org/10.3992/jgb.5.2.129

Reddy, V.S., 2016. Sustainable construction: Analysis of its costs and financial benefits. International Journal of Innovative Research in Engineering and Management (IJIREM), [e-journal] 3(6), pp.522-25. https://doi.org/10.21276/ijirem.2016.3.6.12

Ribas, J.R., Arce, M.E., Sohler, F.A. and Suárez-García, A., 2019. Multi-criteria risk assessment: Case study of a large hydroelectric project. Journal of Cleaner Production, [e-journal] 227, pp.237-47. https://doi.org/10.1016/j.jclepro.2019.04.043

RICS, 2015. Management of Risk: RICS professional note. 1st ed. London, UK: Royal Institute of Chartered Surveyors. Available at: www.rics.org/guidance. [Accessed 10 July 2020].

Robichaud, L.B. and Anantatmula, V.S., 2011. Greening Project Management Practices for Sustainable Construction. Journal of Management in Engineering, [e-journal] 27(1), pp.48–57. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000030

Sekaran, U. and Bougie, R.J., 20016. Research Methods for Business: A Skill Building Approach. 7th ed. New York: Wiley.

Susanti, B. Filestre, S.F.H. and Juliantina, I., 2019. The analysis of barriers for implementation of sustainable construction in Indonesia. The 2nd International Conference on Smart City Innovation, IOP Conference Series: Earth and Environmental Science, 396, p.012033. https://doi.org/10.1088/1755-1315/396/1/012033

Taherdoost, H. 2017. Determining sample size; How to calculate survey sample size. International Journal of Economics and Management Systems, 2, pp.237- 39.

Taroun, A., 2014. Towards a better modelling and assessment of construction risk: Insight from a literature review. International Journal of Project Management, [e-journal] 32(1), pp.101-15. https://doi.org/10.1016/j.ijproman.2013.03.004

The University of Melbourne., 2017. Risk assessment methodology. Melbourne Australia: UM. Available at: https://safety.unimelb.edu.au. [Accessed 15 July 2020].

Thomas, N.I.R., Costa, D.B. and Guimarães, M.S.O., 2013. Identification of the primary needs for sustainability and improvements in working conditions on construction sites. Proceedings of CIB World Congress, Brisbane.

Tollin, H.M., 2011. Green building risks: It is not easy being green. Environmental Claims Journal, [e-journal] 23(3-4), pp.199-213. https://doi.org/10.1080/10406026.2011.593442

Tong, R., Cheng, M., Zhang, L., Liu, M., Yang, X., Li, X. and Yin, W., 2018. The construction dust-induced occupational health risk using Monte-Carlo simulation. Journal of Cleaner Production, [e-journal] 184, pp.598-608. https://doi.org/10.1016/j.jclepro.2018.02.286

USGBC, 2010. Green building design and construction. Available at: www.epa.gov/iaq/pubs/sbs.html [Accessed 28 November 2020].

Wang, S.Q., Dulami, M.F. and Agar, M.Y., 2004. Risk management framework for construction projects in developing countries. Construction Management and Economics, [e-journal] 22(3), pp.237-52. https://doi.org/10.1080/0144619032000124689

Wang, Y., Han, Q., de Vries, B. and Zuo, J., 2016. How the public reacts to social impacts in construction projects? A structural equation modelling study. International Journal of Project Management, [e-journal] 34(80), pp.1433-48. https://doi.org/10.1016/j.ijproman.2016.07.008

Willar, D., Waney, E.V.Y., Pangemanan, D.D.G. and Mait, R.E.G., 2021. Sustainable construction practices in the execution of infrastructure projects: The extent of implementation. Smart and Sustainable Built Environment, [e-journal] 10(1), pp.106-24. https://doi.org/10.1108/SASBE-07-2019-0086

Wiseman, F., 2003. On the reporting of response rates in extension research. Journal of Extension, 41(3). Available at: http://www.joe.org/joe/2003june/comm1.php [Accessed 8 December 2021].

Workplace Safety and Health Council, 2011. Code of practice on workplace safety and health (WSH) risk management. The Workplace Safety and health Council in collaboration with the Ministry of Manpower. Available at: www.wshc.sg [Accessed 15 July 2020].

Wu, Z., Jiang, M., Cai, Y., Wang, H. and Li, S., 2019a. What Hinders the Development of Green Building? An Investigation of China. International Journal of Environmental Research and Public Health, [e-journal] 16(17), p.3140. https://doi.org/10.3390/ijerph16173140

Wu, P., Xu, Y., Jin, R., Lu, Q., Madgwick, D. and Hancock, C.M., 2019b. Perceptions towards risks involved in off-site construction in the integrated design & construction project delivery. Journal of Cleaner Production, e-journal] 213, pp. 899-914. https://doi.org/10.1016/j.jclepro.2018.12.226

Wuni, I.Y. and Shen, G.Q., 2020. Fuzzy modelling of the critical failure factors for modular integrated construction projects. Journal of Cleaner Production, [e-journal] 264, p.121595. https://doi.org/10.1016/j.jclepro.2020.121595

Xia, B., Zuo, J., Wu, P. and Ke, Y., 2015. Sustainable construction trends in journal papers. In: L. Shen, K. Ye and C. Mao, Eds. Proceedings of 19th International Symposium on Advancement of Construction Management and Real Estate, Chongqing, China: Springer, pp.169-79. https://doi.org/10.1007/978-3-662-46994-1_15

Xiahuo, X., Tang, Y., Yuan, J., Chand, T., Liu, P. and Li, Q., 2018. Evaluating social performance of construction projects: An empirical study. Sustainability, [e-journal] 10(7), p.2329. https://doi.org/10.3390/su10072329

Xiang T. and Shu X.Y., 2018. Identification of risk in green building projects based on the perspective of sustainability. IOP Conference Series: Materials Science and Engineering, 439, p.032053. https://doi.org/10.1088/1757-899X/439/3/032053

Yang, R.J., Zou, P.X.W. and Wang, J., 2016. Modelling stakeholder-associated risk networks in green building projects. International Journal of Project Management, [e-journal] 34(1), pp.66-81. https://doi.org/10.1016/j.ijproman.2015.09.010

Yin, B.C.L., Laing, R., Leon, M. and Mabon, L., 2018. An evaluation of sustainable construction perceptions and practices in Singapore. Sustainable Cities and Society, [e-journal] 39, pp.613-20. https://doi.org/10.1016/j.scs.2018.03.024

Yuan, J., Chen, K., Li, W., Ji, C., Wang, Z. and Skibniewski, M.J., 2018. Social network analysis for social risks of construction projects in high-density urban areas in China. Journal of Cleaner Production, [e-journal] 198, pp.940-61. https://doi.org/10.1016/j.jclepro.2018.07.109

Young T.J., 2016. Questionnaires and surveys. In: Z. Hua, ed. Research methods in intercultural communication: A practical guide. Oxford: Wiley, pp.165-80. https://doi.org/10.1002/9781119166283.ch11

Zhao, X., Hwang, B.G. and Gao, Y., 2016. A fuzzy synthetic evaluation approach for risk assessment: A case of Singapore’s green projects. Journal of Cleaner Production, [e-journal] 115, pp.203-13. https://doi.org/10.1016/j.jclepro.2015.11.042

Zou, J. and Zhao, Z.Y., 2014. Green building research-current status and future agenda: A review. Renewable and Sustainable Energy Reviews, [e-journal] 30, pp.271-81. https://doi.org/10.1016/j.rser.2013.10.021

Zou, P.X.W. and Couani, P., 2012. Managing risks in green building supply chain. Architectural Engineering and Design Management, [e-journal] 8(2), pp.143-58. https://doi.org/10.1080/17452007.2012.659507

Zou, P.X.W., Zhang, G. and Wang, J., 2007. Understanding the key risks in construction projects in China. International Journal of Project Management, [e-journal] 25(6), pp.601–14. https://doi.org/10.1016/j.ijproman.2007.03.001