Identifying Risk Factors of Boot Procurement: A Case Study of Stadium Australia

Marcus Jefferies, Swee Eng Chen


Abstract

Private sector input into the procurement of public works and services is continuing to increase. This has partly arisen out of a requirement for infrastructure development to be undertaken at a rate that maintains and allows growth. This has become a major challange for the construction industry that cannot be met by government alone. The emergence of Build-Own-Operate-Transfer (BOOT) schemes as a response to this challange provides a means for developing the infrastructure of a country without directly impacting on the governments budgetary constraints. The concepts of BOOT are without doubt extremely complex arrangements, which bring to the construction sector risks not experienced previously. Many of the infrastructure partnerships between public and private sector in the pastare yet to provide evidence of successful completion, since few of the concession periods have expired. This paper provides an identified list of risk factors to a case study of Stadium Australia. The most significant risk associated with Stadium Australia include the bidding process, the high level of public scrutiny, post-Olympic Games facility revenue and the complicated nature of the consortium structure.  

Keywords

Build-Own-Operate-Transfer (BOOT), Case study, Infrastructure, Risk factors, Stadium Australia, Sustainable procurement

Full Text

PDF

References

Akintoye, A. and Taylor, C. (1997) Risk Prioritisation of Private Sector Finance of Public Sector Projects. In (Eds) Davidson, C.H. and Abdel Meguid, T.A. Procurement . A Key to Innovation, Proceedings of CIB W92 International Symposium, Montreal, pp 1-10, ISBN 0-9682215-0-5.

Angeles, N.H. and Walker D. (2000) BOOT Schemes . A Project Delivery System for a New Millenium. Chartered Building Professional, March 2000, pp 21-23, ISSN 1324-0990.

Fellows, R. and Liu, A. (1997) Research Methods For Construction. London, Blackwell Science.

Jefferies, M.C. (2003) Risk and Critical Success Factors of the Build-Own-Operate-Transfer Approach. Unpublished Research Masters Thesis, University of Newcastle, Australia.

Jefferies, M.C., Cook, M. and Rowlinson S. (2001) The BOOT Approach for Stadium Australia: Reflecting on the Critical Factors for Success. In (ed) Duncan, J. Performance in Product and Practice, Proceedings of the CIB World Building Congress, 2-6 April, Wellington, NZ.

Jefferies, M.C. and Gameson, R. (2002) Stadium Australia: Reflecting on the Risk Factors of BOOT Procurement. In (Ed) Lewis, T.M., Procurement Systems and Technology Transfer, CIB W92 Procurement Systems Symposium, The University of The West Indies, Trinidad and Tobago, January 14-17, pp 355-368.

Ma, T.Y.F., Chan, A. and Lam P.T.I. (1998) A Study Into The Characteristics of BOT projects in Hong Kong. The 6th East Asia-Pacific Conference on Structural Engineering and Construction, Taipei, Taiwan, pp1131-1136.

Magub, A and Hampson K. (1999) Sydney.s Oylmpic Stadium: A World Class Event? Construction Process Re-enginnering .99, Proceedings of the International Conference for Construction Process Re-engineering, 12-13 July, UNSW, Sydney, pp 121-132.

McDermott, P. (1999) Strategic and Emergent Issues in Construction Procurement. In (eds) Rowlinson S. and McDermott, P., Procurement Systems: A Guide to Best Practice, E. and F.N. Spon, London, pp 3-26.

Miller, J.B. (1997) Procurement Strategies Which Encourage Innovation: The Fundamental Element of Sustainable Public Infrastructure Systems. In (Eds) Davidson, C.H. and Abdel Meguid, T.A. Procurement . A Key to Innovation, Proceedings of CIB W92 International Symposium, Montreal, pp 443-452. ISBN 0-9682215-0-5 null

11 NSW Government (1997) Guidelines for Private Sector Participation in the Provision of Public Infrastructure. NSW Government, Department of State and Regional Development."

New South Wales Government (2000) Working with Government . Private Financing of Infrastructure and Certain Government Services in NSW. NSW Government Green Paper.

Salzmann A., Mohamed S. (1999) Risk Identification Frameworks for International BOOT Projects. In (ed) Ogunlana S. Profitable Partnering in Construction Procurement, CIB W92 Proceedings Publication 224, pp 475-485, ISBN 0-419-24760-2.

Smith A.J. (1999) Privatized Infrastructure: The Role of Government. Thomas Telford, London. http://dx.doi.org/10.1680/pitrog.27121

Stadium Australia Group (1996a) Stadium Australia Group -Summary of Material Contracts. Sydney, Stadium Australia Group.

Stadium Australia Group (1996b) Stadium Australia Group -Price Waterhouse Corporate Finance- Independent Accountant.s Report. September 1996, Sydney, Stadium Australia Group.

United Nations Industrial Development Organisation (1996) Guidelines for Infrastructure Development through Build-Operate-Transfer (BOT) Projects. UNIDO, Vienna.

Walker C. and Smith A.J. (1995) Privatized Infrastructure: The BOT Approach. London, Thomas Telford. http://dx.doi.org/10.1680/pitba.20535

Walker, D.H.T., Hampson, K. and Peters, R. (2000) Relationship Based Procurement Strategies for the 21st Century. AusInfo, Canberra.

Yin, R.K. (1984) Case Study Research Design and Methods. California, Sage Publications.

Article Metrics

Metrics Loading ...

Metrics powered by PLOS ALM