An Investigation into Factors Influencing Construction Costs Based on Japanese, UK and US Contractor Practice

Hong Xiao, David Proverbs


Abstract

Construction cost is a major concern to both clients and contractors. Based on a hypotheticalconstruction project (a six-storey concrete framed office building), cost and otherrelated information was collected through a survey of contractors in Japan, the UK and theUS. Using multiple regression analysis it was found that lower overheads, less prefabricatedcomponents, and fewer design variations could reduce construction cost. Overheadslargely represent indirect costs to contractors and if reduced can lead to increased profitlevels and improved competitiveness. The use of prefabricated components may be problematicwhere there are delays in production, insufficient coordination between design andconstruction, and congested transportation on site. Design variations during constructionbring about uncertainties and are disruptive to the construction process. These factorshave paramount impact on construction cost and demand close attention and consideration.Contractors are advised to reduce the costs of their overheads and utilise prefabricationappropriately, while clients and designers should minimise the number of designvariations during construction if better cost performance is desired.

Full Text

PDF

References

Adeli, H. and Wu, M. (1998) Regularization neural network for construction cost esti-mation. Journal of Construction Engineering and Management, 124 (1), 18–24. http://dx.doi.org/10.1061/(ASCE)0733-9364(1998)124:1(18)

Ahmed, S.M. and Kangari, R. (1995) Analysis of client-satisfaction factors in construction industry. Journal of Management in Engi-neering, 11 (2), 36–44. http://dx.doi.org/10.1061/(ASCE)0742-597X(1995)11:2(36)

Akinci, B. and Fischer, M. (1998) Factors affecting contractors' risk of cost overbur-den. Journal of Management in Engineering, 14 (1), 67–76. http://dx.doi.org/10.1061/(ASCE)0742-597X(1998)14:1(67)

Akintoye, A. (1995) Just-in-Time application and implementation for building material management. Construction Management and Economics, 13, 105–13. http://dx.doi.org/10.1080/01446199500000013

d'Arcy, J. (1995) Cutting costs by 30%. Con-tract Journal, 13 April, 1995, 18–20.

Arditi, D.; Ergin, U. and Gunhan, S. (2000) Factors affecting the use of precast con-crete systems. Journal of Architectural En-gineering, 6 (3), 79–86. http://dx.doi.org/10.1061/(ASCE)1076-0431(2000)6:3(79)

Ashworth, A. (1996) Pre-contract Studies: Development Economics, Tendering and Estimating. Addison Wesley Longman Lim-ited, Harlow.

Ball, M.; Farshchi, M. and Grilli, M. (2000) Competition and the persistence of profits in the UK construction industry. Construction Management and Economics, 18, 733–45. http://dx.doi.org/10.1080/014461900433023

Brook, M. (1998) Estimating and Tendering for Construction Work (Second Edition). But-terworth-Heinemann, Oxford.

Chan, A.P.C. and Yeong, C.M. (1995) A com-parison of strategies for reducing variations. Construction Management and Economics, 13, 467–73. http://dx.doi.org/10.1080/01446199500000054

Chartered Institute of Building (2000) Direc-tory and list of members–Chartered Insti-tute of Building, Chartered Institute of Building, Stonehart Group, London null

12 Chau, K.W. (1999) On the issue of plan shape complexity: plan shape indices revisited. Construction Management and Economics, 17, 473–82." http://dx.doi.org/10.1080/014461999371394

CIDA (Construction Industry Development Agency) (1993) Key performance Criteria. Construction Industry Development Agency, Melbourne, Australia.

Davenport, D. (1997) Client satisfaction with construction cost–a comparative study of French and UK performance. Journal of Fi-nancial Management of Property and Con-struction, 2 (3), 77–94.

Dissanayaka, S.M. and Kumaraswamy, M.M. (1999) Comparing contributors to time and cost performance in building projects. Building and Environment, 34 (1), 31–42. http://dx.doi.org/10.1016/S0360-1323(97)00068-1

Edkins, A. and Winch, G. (1999) The Per-formance of the UK Construction Industry: An International Perspective. University Col-lege London, London.

Elhag, T.M.S. and Boussabaine, A.H. (1998) An artificial neural system for cost estima-tion of construction projects. ARCOM Four-teenth Annual Conference 1998, University of Reading, pp. 219–26.

Hair, Jr., J.F., Anderson, R.E., Tatham, R.L. and Black, W.C. (1995) Multivariate Data Analysis with Readings, 4th Edition. Prentice-Hall International, Inc., Englewood Cliffs, New Jersey.

Hegazy, T. and Ayed, A. (1998) Neural net-work model for parametric cost estimation of highway projects. Journal of Construction Engineering and Management, 124 (3), 210–18. http://dx.doi.org/10.1061/(ASCE)0733-9364(1998)124:3(210)

Ireland, V. (1985) The role of managerial ac-tions in the cost, time and quality perform-ance of high-rise commercial building projects. Construction Management and Economics, 3, 59–87. http://dx.doi.org/10.1080/01446198500000006

Ishai, E. (1989) Architectural and economic considerations in the design of prefabricated fa–ade components (exterior walls). Construction Management and Economics, 7, 189–202. http://dx.doi.org/10.1080/01446198900000022

Johnson, R.A. and Wichern, D.W. (1998) Ap-plied Multivariate Statistical Analysis. Pren-tice-Hall, Inc., Upper Saddle River, New Jersey.

Kaming, P.F.; Olomolaiye, P.O.; Holt, G.D. and Harris, F.C. (1997) Factors influencing construction time and cost overruns on high-rise projects in Indonesia. Construction Management and Economics, 15, 83–94. http://dx.doi.org/10.1080/014461997373132

Kravis, I.B. (1984) Comparative studies of national incomes and prices. Journal of Economic Literature, 22(March), 1–39.

Low, S.P. and Choong, J.C. (2001) Just-In-Time management of precast concrete components. Journal of Construction Engi-neering and Management, 127 (6), 494–501. http://dx.doi.org/10.1061/(ASCE)0733-9364(2001)127:6(494)

Low, S.P. and Mok, S.H. (1999) The applica-tion of JIT philosophy to construction: a case study in site layout. Construction Manage-ment and Economics, 17, 657–68. http://dx.doi.org/10.1080/014461999371268

Naoum, S. G. and Mustapha, F. H. (1995) Relationship between the building team, procurement methods and project perform-ance. Journal of Construction Procurement, 1 (1), 50–63.

Newbold, P. and Bos, T. (1990) Introductory Business Forecasting. South Western Publishing, Cincinnati.

Norusis, M.J. (1995) SPSS: SPSS 6.1 Guide to Data Analysis. Prentice-Hall, Inc., New Jersey.

OECD (2001) Purchasing power parities. Or-ganisation for Economic Co-operation and Development, http://www.oecd.org/std/ppp/pps.htm (updated on 24/01/2001, accessed on 22/03/2001).

Proverbs, D.G. (1998) A best practice model for high-rise in situ concrete construction based on French, German and UK contrac-tor performance measures. Ph.D. Thesis, University of Wolverhampton.

Reed Business Information (1999) KOMPASS: Products and Services Register 1, 1999/2000 United Kingdom. Reed Busi-ness Information, East Frinstead, West Sus-sex.

Singh, S. (1990) Cost model for reinforced concrete beam and slab structures in build-ings. Journal of Construction Engineering and Management, 116 (1), 54–67. http://dx.doi.org/10.1061/(ASCE)0733-9364(1990)116:1(54)

Tah, J.H.M., Thorpe, T. and McCaffer, R. (1994) A survey of indirect cost estimating in practice. Construction Management and Economics, 12, 31–6. http://dx.doi.org/10.1080/01446199400000004

Tam, C.M. and Harris, F. (1996) Model for assessing building contractors' project per-formance. Engineering, Construction and Architectural Management, 3|3, 187–203.

Wallace, I.N.D. (1995) Hudson's Building and Engineering Contracts (11th Edition). Sweet and Maxwell, London.

Vermande, H. M. and Van Mulligen, P. (1999) Construction costs in The Netherlands in an international context. Construction Man-agement and Economics, 17, 269–83. http://dx.doi.org/10.1080/014461999371484

Xiao, H., Proverbs, D., Shaw, T. and Holt, G. (2000) A new approach to comparing the performance of contractors internationally. ARCOM Sixteenth Annual Conference 2000, Glasgow Caledonian University, pp. 117–25.

Xiao, H., Proverbs, D., and Holt, G. (2002) A New Paradigm for International Contractor Performance Assessment. Journal of Con-struction Research (accepted).

Xiao, H. and Proverbs, D.G. (2002) The per-formance of contractors in Japan, the UK and the US: a comparative evaluation of construction cost. Construction Manage-ment and Economics, (accepted). http://dx.doi.org/10.1080/01446190210145859