Performance of Design-Build Projects in terms of Cost, Quality and Time: Views of Clients, Architects and Contractors in Singapore

Florence Ling, Edwin Leong


Abstract

One of the major problems in the construction industry is that of fragmentation. This hasled to an increased adoption of design-build (DB) as a procurement route in recent years.This move attempts to solve problems associated with the use of the traditional designbid-build method.The performance of DB projects is investigated under three aspects, namely quality, timeand cost. Results of the opinion survey concluded that contractors, architects and clientsagreed that DB projects perform well in these three areas. This confirms the inherent advantagesthat DB has to offer. It is concluded that DB is indeed a worthwhile procurementroute but the various participants must understand its structure and accept the changesinvolved.

Full Text

PDF

References

Akintoye, A. (1994) Design and build: a sur-vey of construction contractors' views. Con-struction Management and Economics, 12, 155–163. http://dx.doi.org/10.1080/01446199400000021

Akintoye, A. and Fitzgerald, E. (1995) Design and build: a survey of architects' views. En-gineering, Construction and Architectural Management, 2 (1), 27–44. http://dx.doi.org/10.1108/eb021001

Anumba, C.J. and Evbuomwan, N.F.O. (1997) Concurrent engineering in design-build pro-jects. Construction Management and Eco-nomics, 15, 271–281. http://dx.doi.org/10.1080/014461997373006

Bennett, J., Pothecary, E. and Robinson, G. (1996) Designing and building a world-class industry. Centre for Strategic Studies in Construction, Reading.

Caunce, J. (1995) Hybrid pretenders threaten D & B image. Construction Man-ager, 1 (1), 21.

Chan, A.P.C. and Lam, P.T. (1995) Novation contract: an innovative variation to design-build. In: Proceedings of the First Interna-tional Congress on Construction: Design and Build Projects – International Experi-ences, 197–203. National University of Sin-gapore, Singapore.

Chan, A.P.C. (2000) Evaluation of enhanced design and build system – a case study of a hospital project. Construction Management and Economics, 18, 863–871. http://dx.doi.org/10.1080/014461900433140

Chan, A.P.C., Ho, D.C.K. and Tam, C.M. (2001) Design and build project success fac-tors: multivariate analysis. Journal of Con-struction Engineering and Management, ASCE, 127, 93–100. http://dx.doi.org/10.1061/(ASCE)0733-9364(2001)127:2(93)

Chappell, D. (1991) Which form of building contract. Architecture Design and Technol-ogy Press, London.

Chartered Institute of Building (1988) Code of estimating practice supplement number two: design and build, Supplement 2. CIOB, London.

Chevin, D. (1993) Client survey: fitting the bill. Building – Design and Build Supple-ment, 30, July, 4–5.

Ernzen, J.J. and Schexnayder, C. (2000) One company's experience with design/build: labor cost risk and profit potential. Journal of Construction Engineering and Manage-ment, ASCE, 126, 10–14. http://dx.doi.org/10.1061/(ASCE)0733-9364(2000)126:1(10)

Hall, M. and Tomkins, C. (2001) A cost of quality analysis of a building project: to-wards a complete methodology for design and build. Construction Management and Economics, 19, 727–740. http://dx.doi.org/10.1080/01446190110066146

Hashim, M. (1996) Characteristics of Design and Build from the Clients' Perspective. In: Proceedings of the International Congress on Construction. Design and Build Projects: International Experiences, 59–62. National University of Singapore, Singapore.

Janssens, D.E.L. (1991) Design-build ex-plained. Macmillan, London.

Katsanis, C.J. and Davidson, C.H. (1998). Horizon 2020: Design-Build. In: Proceedings of CIB World Building Congress – construction and the environment, 2025–2032, G–vle, Sweden.

Konchar, M and Sanvido, V. (1998) Compari-son of US project delivery systems. Journal of Construction Engineering and Manage-ment, 124 (6), 435–444. http://dx.doi.org/10.1061/(ASCE)0733-9364(1998)124:6(435)

Ling, Y.Y. (1995) Evaluation of design and build techniques in Singapore. Focus on Property and Construction in Singapore, 6, 63–67.

Molenaar, K.R., Songer, A.D. and Barash, M. (1999) Public Sector Design/Build Evolution and Performance. Journal of Management in Engineering, 15 (2), 54–62. http://dx.doi.org/10.1061/(ASCE)0742-597X(1999)15:2(54)

Moore, D.R. and Dainty, A.R.J. (2001) Intra-team boundaries as inhibitors of perform-ance improvement in UK design and build projects: a call for change. Construction Management and Economics, 19, 559–562. http://dx.doi.org/10.1080/01446190110055508

Murray, J.P. (1995) Effective briefing: the key to project success. In Proceedings of the First International Congress on Construc-tion: Design and Build Projects – Interna-tional Experiences, 72–80. National University of Singapore, Singapore.

Napier, T.R. and Freiburg, S.R. (1990) One-step and two-step facility acquisition for military construction : Project selection and implementation procedures. Technical Re-port No. p-90/23, US Army Corps of Engi-neers, Construction Engineering Research Laboratory, Champaign, Illinois.

Newbold, P. (1991) Statistics for business and economics (3rd ed.) Prentice Hall, Englewood Cliffs.

Ndekugri, I. and Church, R. (1996) Construc-tion procurement by the design and build approach: a survey of problems. In: Taylor, R.G. (Ed.) Proceedings of CIB W92 – pro-curement systems, North meets South: de-veloping ideas, 452–462. Department of Property Development and Construction Economics, University of Natal, Durban.

Ndekugri, I. and Turner, A. (1994) Building procurement by design and build approach. Journal of Construction Engineering and Management, 120 , 243–256. http://dx.doi.org/10.1061/(ASCE)0733-9364(1994)120:2(243)

NJCC (1985) Code of procedure for selective tendering for design and build. National Joint Consultative Committee, London.

Pain, J. and Bennett, J. (1988) JCT with con-tractor's design form of contract: a study in use. Construction Management and Eco-nomics, 6, 307–337. http://dx.doi.org/10.1080/01446198800000026

Pena-Mora, F. and Li, M. (2001) Dynamic planning and control methodology for de-sign/build fast-track construction projects. Journal of Construction Engineering and Management, ASCE, 127, 1–17. http://dx.doi.org/10.1061/(ASCE)0733-9364(2001)127:6(445)

Rowlinson, S. (1987) Design build – its de-velopment and present status. CIOB, Ascot.

Songer, A.D. and Molenaar, K.R. (1996) Se-lecting design-build: public and private sec-tor owner attitudes. Journal of Management in Engineering, 12 (6), 47–53. http://dx.doi.org/10.1061/(ASCE)0742-597X(1996)12:6(47)

Tam, C.M. (2000) Design and build on a complicated redevelopment project in Hong Kong: The Happy Valley racecourse redevel-opment. International Journal of Project Management, 18, 125–129. http://dx.doi.org/10.1016/S0263-7863(99)00012-5

Turner, D.F. (1995) Design and build con-tract practice (2nd ed.). Longman Scientific and Technical, Harlow.

Walker, M. (1995) Changing Attitudes. New Builder, 23 June, 26–28.

Article Metrics

Metrics Loading ...

Metrics powered by PLOS ALM